CAPM Practice Exam 150 Questions & Answers 2023/2024.
- The process of establishing clear and achievable objectives, measuring their
achievement, and adjusting performance in accordance with the results of the
measurement is called:
- Management by Objectives
- During the full life cycle of the project, a plot of the project’s expected expenditures
will usually follow a characteristic S curve. This indicates that:
- The bulk of the project budget will be spent in the execution phase
- In which project lifecycle phase would you expect to have the greatest influence on
overall project cost?
- Concept
- Requirement is –
- Quantified and documented needs of stakeholders, customer, and sponsor
- TQM is –
- Total Quality Management: A common approach to implementing a quality
improvement program
- Which describes Management Information Systems?
- Software that an enterprise uses to support business and administrative operations
- The type of planning that is equated with more specific data or is detailed in nature is
called:
- Tactical
- What are the different types of costs in Microsoft Project?
- Fixed Cost, Cost Per Use, Standard Cost, Overtime Cost
- What is the name of PMI’s Organization maturity model for project management?
- OPM3
- A group of related projects that are managed in a coordinated way that usually
includes an element of ongoing activity is called a:
- Program
- Project constraint could be on –
- Cost, resources, schedule
- What is true about Project Management Office (PMO)?
- Support Project Managers by coaching and mentoring
PMO is a project stakeholder
PMO can terminate projects if required to keep business objectives consistent
- Projects require project management while operations require business process
management or operations management. Projects can intersect with operations at
various points during the product lifecycle. Which of the following is not a stage to
represent this?
- At each Executing phase
- Enterprise environmental factors refer to both internal and external environmental
factor that surround or influence a project’s success. Of the following, which is NOT an
enterprise environmental factor :
- Historical data
- A person who is involved in or may be affected by the activities or anyone who has
something to gain or lose by the activity of the project is called a:
- Stakeholder
- Large projects may be divided into smaller, more manageable components known
as,
- subprojects
- A manager who manages a group of related projects is called a –
- Program manager
- Which activity is conducted last as part of closing process group
- Customer satisfaction survey
- In the PMBOK, each process is broken into –
- Inputs and Outputs
Tools and techniques
- A stakeholder has the greatest ability to influence a project during –
- Initiation and Planning
- A Project Manager should support making changes during Execution –
- When they are warranted and inline with the strategic goals of the organization
- Conducting Lessons Learned is a critical part of –
- Closing
- Which is not a process from the Planning Process Group?
- Perform Quality Assurance
- The Change Management Plan should be included in which of the following?
- Project Management Plan
- Who is a Project Initiator?