Smartsheet Certification 2023/ 2024 Exam () 100% Correct | Questions and Verified Answers | Graded A
Smartsheet Certification 2023/ 2024 Exam ()
100% Correct | Questions and Verified
Answers | Graded A
QUESTION
Which column type would be best for tracking when a row was added to a sheet?
Date column
Created by System column
Auto-Number column
Created (Date) System column
Answer:
Auto-Number column
QUESTION
You want to keep track of new attachments as they are added to a sheet. Which of the following
is the best way to achieve this goal?
Create a conditional formatting rule to highlight rows with new attachments
Audit Activity Log daily
Create an alert to notify you when an attachment is added or changed
Instruct collaborators to @mention you in the comments after an attachment has been uploaded
Answer:
Create an alert to notify you when an attachment is added or changed
QUESTION
Which of the following file types can be imported as a new sheet in Smartsheet? (select the four
that apply)
MS Project
JIRA Project
Excel
Smartsheet Sheet
Trello
Google Sheets
Answer:
MS Project, Excel, Trello, Google Sheets
QUESTION
A sheet can be exported in which of the following formats? Select ALL that apply.
MS Project (XML)
PDF
Google sheet
Excel
Gantt to image (PNG)
Trello
Answer:
MS Project (XML), PDF, Google Sheet, Excel, Gantt to image (PNG)
QUESTION
Which column type would be best for visually representing (via color) the status of a row item?
This could also be automatically changed using a formula.
Symbol column
Dropdown List column
Text/Number column
System Generated column
Answer:
Symbol column
QUESTION
Which three of the following items can be viewed without a Smartsheet account?
Form
Published dashboard
Report in a workspace shared to you
Update request
Answer:
Form, Published dashboard, and Update request
QUESTION
Which three of the following file types can be uploaded using the image widget?
PDF
PNG
GIF
JPEG
Answer:
PNG, GIF, JPEG
QUESTION
How can you add more fields to your report beyond what fields are used as criteria?
From the File menu select Add More Columns
In the Report Builder, click the Columns button and select additional columns
Add a column to a source sheet. This new column will automatically be displayed in the report.
In the toolbar, click the Report Tool and select additional criteria
Answer:
In the Report Builder, click the Columns button and select additional columns
QUESTION
What is the name for the type of link that contains data linked from another sheet? (Note: This is
designated with a blue arrow on the right side of the cell).
Destination
Outbound
Inbound
Source
Powered by https://learnexams.com/search/study?query=

What is the purpose of installing an auxiliary boom point sheave to the main boom tip?
Separate hoist lines
3 MULTIPLE CHOICE OPTIONS
A designated Lift Director shall be assigned by the __?
Site Supervisor
3 MULTIPLE CHOICE OPTIONS
Who is responsible for calculating net capacity?
Crane Operator
3 MULTIPLE CHOICE OPTIONS
Who is responsible for ensuring all rigging is supervised by a Qualified Rigger?
Site Supervisor/ Lift Director
3 MULTIPLE CHOICE OPTIONS
Who is responsible for ensuring the crane owner is notified of any damage to the crane or replacement/repair of wire rope?
Crane User
3 MULTIPLE CHOICE OPTIONS
Who is responsible for restricting unauthorized access to the crane’s work area?
Site Supervisor/Lift Director
3 MULTIPLE CHOICE OPTIONS
Who is responsible for ensuring the crane owner is notified of any damage to the crane or replacement/repair of wire rope?
Crane User
3 MULTIPLE CHOICE OPTIONS
Who is responsible for ensuring crane operations are stopped if alerted to an unsafe condition?
Lift Director
3 MULTIPLE CHOICE OPTIONS
If the operator or A/D determine that ground conditions are not suitable for the equipment being operated, they should request the _ correct the issue
Controlling Entity
3 MULTIPLE CHOICE OPTIONS
Who is responsible for ensuring that personnel involved in crane operations understand their responsibilities, assigned duties and associated hazards?
Lift Director
3 MULTIPLE CHOICE OPTIONS
When can the operator of a crane set the crane up with less than fully extended outriggers?
When the load chart allows
3 MULTIPLE CHOICE OPTIONS
The outrigger pad and cribbing should be strong enough to support?
The total weight of the crane and the load
3 MULTIPLE CHOICE OPTIONS
What must be known prior to setting up your crane?
Location of underground vaults
3 MULTIPLE CHOICE OPTIONS
What is the minimum distance the flange on the hoist drum should extend above the last wrap of rope?
½ inch
3 MULTIPLE CHOICE OPTIONS
Eccentric main boom tip reeving will
Twisting of the boom
3 MULTIPLE CHOICE OPTIONS
What is the most common wire rope used on most cranes?
Right regular lay
3 MULTIPLE CHOICE OPTIONS
Prior to leveling a crane what should be done with the outrigger jack?
Secure the float pad to jack cylinder
3 MULTIPLE CHOICE OPTIONS
What three functions will not work after two-blocking a crane that has a prevention system?
Boom down, extend the boom and hoist
3 MULTIPLE CHOICE OPTIONS
Boom angle on a telescoping boom is measured from above or below horizontal to the _?
Longitudinal axis of the boom base section
3 MULTIPLE CHOICE OPTIONS
The line pull of the innermost layer on the hoist drum is __________than the outermost layer.
Greater
3 MULTIPLE CHOICE OPTIONS
Side loading of a crane can be caused by?
Wind
3 MULTIPLE CHOICE OPTIONS
If power fails to the crane what must the operator ensure is done?
The controls are put in the neutral position
3 MULTIPLE CHOICE OPTIONS
On a multiple crane lift, do not exceed _ of the load chart.
75%
3 MULTIPLE CHOICE OPTIONS
If a crane operator knows the boom length and the boom angle he could use the range diagram to estimate what?
Load radius
3 MULTIPLE CHOICE OPTIONS
Which of the following jib offsets will have the least amount of capacity?
30 degrees
3 MULTIPLE CHOICE OPTIONS
When is it okay to make modifications to the structure of the crane’s upper works?
With written permission from the manufacturer
3 MULTIPLE CHOICE OPTIONS
A sudden stop of the hoist on a crane will produce a what?
Dynamic load
When hoisting personnel from a crane, what must be on the crane?
Anti-two block device
3 MULTIPLE CHOICE OPTIONS
What grade of alloy steel chain should be used for hoisting slings?
80
3 MULTIPLE CHOICE OPTIONS
Each time a line passes from the boom point to the load block it is considered a _?
Part of line
3 MULTIPLE CHOICE OPTIONS
Which statement about sling angles is correct?
As sling angle decreases, sling stress increases
3 MULTIPLE CHOICE OPTIONS
When installing a wedge socket end termination on the crane the live section of the rope should be in line with the?
Pin
3 MULTIPLE CHOICE OPTIONS
Which of the following hitches would be best suited for lifting a bundle of items?
Double wrapped choker
3 MULTIPLE CHOICE OPTIONS
If the signal person extends his arm at shoulder height with his thumb pointing down what do they want the operator to do?
Boom down
3 MULTIPLE CHOICE OPTIONS
If the signal person has their arm extended and is pointing to his/her left, what do they want you to do?
Swing right
3 MULTIPLE CHOICE OPTIONS
Why is a carry deck crane, called a carry deck?
The deck of the crane has carrying capacities
3 MULTIPLE CHOICE OPTIONS
How much clearance is required between the counterweight of the crane and all objects?
2 ft.
3 MULTIPLE CHOICE OPTIONS
Which of the following would be good ground conditions for setting up a crane?
Compacted and level
3 MULTIPLE CHOICE OPTIONS
When using a carpenter’s level to check the level condition of the crane, where would be the best location to put the level?
Swing bearing of the upper works
3 MULTIPLE CHOICE OPTIONS
What is the advantage to placing mats or cribbing under the outrigger floats?
Lowers the ground pressure applied by the crane
3 MULTIPLE CHOICE OPTIONS
When operating a crane within 100 feet of water what degree of level should your crane be?
.57 degrees
3 MULTIPLE CHOICE OPTIONS
When is it ok to place blocking under the outrigger beams of a crane?
Never
3 MULTIPLE CHOICE OPTIONS
What is the purpose of installing a auxiliary boom point sheave to the main boom tip?
Separate hoist lines
3 MULTIPLE CHOICE OPTIONS
Which of the following is considered standing rope?
Pendant line
3 MULTIPLE CHOICE OPTIONS
How many broken wires are allowed in one strand of one lay of standard wire rope?
3
3 MULTIPLE CHOICE OPTIONS
The lubricant used for wire rope should be of what type?
That does not hinder visual inspection
3 MULTIPLE CHOICE OPTIONS
How often should the crane operator inspect standard running wire rope?
Every shift (When in use)
3 MULTIPLE CHOICE OPTIONS
How many broken wires are allowed on 30 diameters of EEIPS rotation resistant wire rope?
4
3 MULTIPLE CHOICE OPTIONS
With the boom at its highest angle and its shortest radius, how many wraps of wire rope need to be on the drum at all times?
2
3 MULTIPLE CHOICE OPTIONS
When measuring load radius of the crane. You measure from the axis of rotation of the crane to the_____?
Center of gravity of the load
3 MULTIPLE CHOICE OPTIONS
What must be deducted from the gross capacity of the crane when the jib is erected, but not in use?
Effective weight
3 MULTIPLE CHOICE OPTIONS
Where can tip height be found?
Range diagram
3 MULTIPLE CHOICE OPTIONS
The Net Capacity of the crane is?
Gross capacity minus all applicable deductions
3 MULTIPLE CHOICE OPTIONS
When booming down with a jib/extension erected the effective weight of the jib_____?
Increases
3 MULTIPLE CHOICE OPTIONS
When using a crane in a duty cycle operation manufacturers usually de-rate the cranes capacity by?
20%
3 MULTIPLE CHOICE OPTIONS
How would the operator of the crane know if the radius on the LMI is correct?
By measuring
3 MULTIPLE CHOICE OPTIONS
According to OSHA, each series of voice signals contain how many elements?
3
3 MULTIPLE CHOICE OPTIONS
What is the first element of voice signals given to a crane operator prior to the lift?
Function and direction
3 MULTIPLE CHOICE OPTIONS
When working within the boom’s length of energized power lines what is required?
A dedicated spotter to maintain safe clearances
3 MULTIPLE CHOICE OPTIONS
What is the first thing the operator should do if the crane comes in contact with an energized power line?
Remain in the cab until power line is de-energized
3 MULTIPLE CHOICE OPTIONS
The weight deduction for a stowed jib is _?
The effective weight
3 MULTIPLE CHOICE OPTIONS
If the boom angle of the crane falls between values on the load chart you should use?
The lower angle
3 MULTIPLE CHOICE OPTIONS
What is the most common type of wire rope used on a crane?
Right regular lay
3 MULTIPLE CHOICE OPTIONS
According to Table A of OSHA 1926.1408 the minimum clearance distance for a power line over 200 KV is?
20 ft.
3 MULTIPLE CHOICE OPTIONS
When lifting from a jib/extension and the main boom is not fully extended. What information must you use to get the gross capacity from the load chart?
Main boom angle
3 MULTIPLE CHOICE OPTIONS
According to Table A of OSHA 1926.1408 the minimum clearance distance for a power line up to 50 KV is?
10 ft.
3 MULTIPLE CHOICE OPTIONS
According to Table A of OSHA 1926.1408 the minimum clearance distance for a power line at 100 KV is?
15 ft.
3 MULTIPLE CHOICE OPTIONS
According to Table A of OSHA 1926.1408 the minimum clearance distance for a power line over 350 KV is?
25 ft.
3 MULTIPLE CHOICE OPTIONS
According to Table A of OSHA 1926.1408 the minimum clearance distance for a power line over 500 KV is?
35 ft.
3 MULTIPLE CHOICE OPTIONS
According to Table A of OSHA 1926.1408 the minimum clearance distance for a power line at 750 KV is?
35 ft.
3 MULTIPLE CHOICE OPTIONS
According to Table A of OSHA 1926.1408 the minimum clearance distance for a power line at 1000 KV is?
45 ft.
3 MULTIPLE CHOICE OPTIONS
If carrying a load on a downward slope, the radius will __?
Increase
3 MULTIPLE CHOICE OPTIONS
If carrying a load on an upward slope, the radius will __?
Decrease
3 MULTIPLE CHOICE OPTIONS
When hoisting personnel, within what percentage of level must a telescopic boom crane be in order for the gross ratings in the load chart to remain valid?
1%
3 MULTIPLE CHOICE OPTIONS
What may happen to a properly rigged load when lifted off the ground unless the operator takes account of boom deflection?
It could swing out away from the crane
3 MULTIPLE CHOICE OPTIONS
Which area do truck cranes without a 5th outrigger generally have no lifting capacity unless the manufacturer states otherwise?
The front
3 MULTIPLE CHOICE OPTIONS
What is the definition of “operating radius?”
The distance from the center of rotation of the crane to the center of gravity of the load
3 MULTIPLE CHOICE OPTIONS
What applies to the capacities below the bold line shown on a load chart?
They are based on the stability of the crane
3 MULTIPLE CHOICE OPTIONS
In which quadrant are rough terrain crane capacities generally greater?
Over the front
3 MULTIPLE CHOICE OPTIONS
According to federal requirements, under what conditions is it okay for a person to ride the headache ball?
It is never okay
3 MULTIPLE CHOICE OPTIONS
By what percentage do most manufacturers require a crane’s load chart capacity to be reduced by for duty cycle operations such as high-volume concrete placement?
20%
3 MULTIPLE CHOICE OPTIONS
What is the preferred method of installing wire rope from a reel onto a hoist drum?
The rope runs from the top of the reel to the top of the drum
3 MULTIPLE CHOICE OPTIONS
Over which quadrant are truck crane capacities usually greater?
Over the rear
3 MULTIPLE CHOICE OPTIONS
According to OSHA, which accessible area of an operating crane must always be barricaded?
The swing radius of the rear of the rotating superstructure
3 MULTIPLE CHOICE OPTIONS
What is the OSHA regulation governing cranes in construction?
1926.1400
3 MULTIPLE CHOICE OPTIONS
Under which circumstance is a crack in the windshield of a crane cab okay?
As long as it causes no visible distortion that would interfere with safe operations
3 MULTIPLE CHOICE OPTIONS
Under which circumstance does OSHA permits hoisting of personnel by crane?
As long as there is no less hazardous or practicable way
3 MULTIPLE CHOICE OPTIONS
Unless the manufacturer states otherwise, what crane capacity chart is appropriate when a crane is set up with 3 of its 4 outriggers extended and the fourth is retracted?
On-rubber chart
3 MULTIPLE CHOICE OPTIONS
According to OSHA, while hoisting personnel, the total load must not exceed what percentage of the crane’s rated capacity?”
50%
3 MULTIPLE CHOICE OPTIONS
When is side loading of crane booms permitted?
Only with freely suspended loads
3 MULTIPLE CHOICE OPTIONS
What is indicated if an operator makes two audible signals when moving a crane?
He/she intends to go ahead
3 MULTIPLE CHOICE OPTIONS
What is the result of placing timber blocking under the tips of the tracks on a crawler crane?
Makes the crane more stable
3 MULTIPLE CHOICE OPTIONS
According to ASME, what percentage of the manufacturer’s crane rating must not be exceeded if a load test is done on a repaired crane?
110%
3 MULTIPLE CHOICE OPTIONS
What should be done with materials placed under overhead energized power lines?
Not be lifted by crane
3 MULTIPLE CHOICE OPTIONS
Where should the crane’s outrigger pads or tracks be placed when working at ground floor level near a cellar wall?
At least as far back as the depth of the wall below ground
3 MULTIPLE CHOICE OPTIONS
What happens to ground bearing pressure if you move a crawler crane from soft ground to harder ground?
It increases
3 MULTIPLE CHOICE OPTIONS
Where are the Standard Method hand signals found?
OSHA Subpart CC Appendix A
3 MULTIPLE CHOICE OPTIONS
What happens to the leverage of the load on a crane as the boom is being lowered?
It increases
3 MULTIPLE CHOICE OPTIONS
When is it okay to temporarily bypass a crane’s overload warning system?
During assembly/disassembly operations
3 MULTIPLE CHOICE OPTIONS
How many parts of line are required to hoist a 36,500 lb. load if the maximum allowable line pull is 9,000 lb.
5
3 MULTIPLE CHOICE OPTIONS
Where should the hook be positioned when preparing to hoist a light load?
Directly above the load’s center of gravity
3 MULTIPLE CHOICE OPTIONS
When using a luffing jib, decreasing the angle will _?
Decrease capacity
3 MULTIPLE CHOICE OPTIONS
Who is responsible for calculating net capacity?
Crane Operator
3 MULTIPLE CHOICE OPTIONS
A swivel on rotation resistant wire rope can be used when __?
The manufacturer gives approval
3 MULTIPLE CHOICE OPTIONS
If the anti-two block is not working properly, an alternative measure is _?
Immediately report to the supervisor and mark the wire rope
3 MULTIPLE CHOICE OPTIONS
When a crane suddenly stops during a lift, the loading on the crane tends to _?
Increase
3 MULTIPLE CHOICE OPTIONS
What type of jib can increase or decrease angle during operation?
Luffing jib
3 MULTIPLE CHOICE OPTIONS
What happens to the leverage of the load on a crane as the boom is being lowered?
It increases
3 MULTIPLE CHOICE OPTIONS
The minimum approach distance for cranes driving, in transit, under power lines that are over 50 kV is _?
10′
3 MULTIPLE CHOICE OPTIONS
During disassembly of a long boom, the pendant lines are connected at the maximum cantilever point and the boom is slightly lifted off the ground. Which pins are to be removed next?
The bottom pins ahead of the cantilever point
3 MULTIPLE CHOICE OPTIONS
Which configuration requires the greatest capacity reduction when out of level?
Long boom, minimum radius
3 MULTIPLE CHOICE OPTIONS
What is the purpose of a Load Moment Indicator?
Aid the operator by displaying relevant information and alert the operator of unsafe conditions.
3 MULTIPLE CHOICE OPTIONS
According to ASME B30.5, how often must a crane operator take a physical exam?
Every 3 years
3 MULTIPLE CHOICE OPTIONS
What is an example of high duty cycle?
High speed concrete operations
3 MULTIPLE CHOICE OPTIONS
While setting a crane up on unstable ground what must the operator ensure?
The stabilizer is 90° to the pad
3 MULTIPLE CHOICE OPTIONS
When a lattice boom is being dismantled __.
Never touch any pin on any boom section located between the pendant attachment points and the crane.
3 MULTIPLE CHOICE OPTIONS
How can an operator ensure the radius being displayed by the LMI is correct?
By proper measurement
3 MULTIPLE CHOICE OPTIONS
What is the purpose of a barge chart?
To account for list and trim
3 MULTIPLE CHOICE OPTIONS
What must be done when working on a barge?
The crane must be secured
3 MULTIPLE CHOICE OPTIONS
According to OSHA subpart CC, when employees are engaged in hooking, unhooking, or guiding the load within the fall zone what type of hook should be used?
J hook
3 MULTIPLE CHOICE OPTIONS
According to OSHA subpart CC, when employees are engaged in hooking, unhooking or guiding the load within the fall zone _
Hooks must have self-closing latches
3 MULTIPLE CHOICE OPTIONS
What is a cantilever section on a lattice boom crane?
The outermost section past the pendant line connection point
3 MULTIPLE CHOICE OPTIONS
An electrocution decal needs to be placed where on the crane?
One in the cab and two on the outside of the crane
3 MULTIPLE CHOICE OPTIONS
What is the capital D referring to in the term D/d ratio, as it related to a basket hitch?
The diameter of the load
3 MULTIPLE CHOICE OPTIONS
If the controlling entity cannot be contacted, who should be notified if there is an issue with ground conditions?
Employer with authority
3 MULTIPLE CHOICE OPTIONS
What is the definition of gross load?
The load weight plus the weight of all attachments/load handling devices
3 MULTIPLE CHOICE OPTIONS
What is the definition of net load?
The actual weight of the load before attachments/load handling devices are factored in
2 MULTIPLE CHOICE OPTIONS
What is the definition of net capacity?
The capacity listed on the load chart given the configuration minus all applicable attachments/load handling devices
3 MULTIPLE CHOICE OPTIONS
The term “center of gravity” means:
The point of an object around which the weight is averaged (concentrated)
3 MULTIPLE CHOICE OPTIONS
ANSI/ASME B30.5 deals with which type of cranes?
Mobile and locomotive
3 MULTIPLE CHOICE OPTIONS
What is the meaning of “boom stop”?
Device used to limit the boom at its highest position.
3 MULTIPLE CHOICE OPTIONS
In order to calculate the working load limit of wire rope, you must:
Divide the breaking strength by the appropriate design factor
3 MULTIPLE CHOICE OPTIONS
“Effective weight” is:
The calculated amount of effect a component will have on the lifting point of a crane
3 MULTIPLE CHOICE OPTIONS
On a lattice boom crane, which position should the gantry be in when lifting a load?
Highest position
3 MULTIPLE CHOICE OPTIONS
Blocking angle type outriggers too high could cause:
Tipping axis reduction
3 MULTIPLE CHOICE OPTIONS
When setting up a mobile crane on uneven ground, you should place blocking under outrigger pontoons so that they are _ the cylinder
Perpendicular (90°) to
3 MULTIPLE CHOICE OPTIONS
The effect of external pressure on wire rope is described as:
Crushing
3 MULTIPLE CHOICE OPTIONS
Due to its tendency to untwist, which of these types of wire rope should NOT be used on single part hoisting lines?
Lang lay
3 MULTIPLE CHOICE OPTIONS
Rotation resistant wire rope sometimes has a lower Working Load Limit than an equal sized regular lay wire rope because:
Rotation resistant wire rope has a higher design factor
3 MULTIPLE CHOICE OPTIONS
At what angle to the horizontal will the stress on each sling leg (using 2 slings) be equal to the weight of the load?
30°
3 MULTIPLE CHOICE OPTIONS
Extra load radius can be caused by:
Rapid swing
3 MULTIPLE CHOICE OPTIONS
When assembling lattice boom sections, which set of pin holes are lined up and pinned first?
The top ones
1 MULTIPLE CHOICE OPTION
Crane stability is based on:
The leverage principle
3 MULTIPLE CHOICE OPTIONS
The effective weight of an attachment is:
Any of these options
3 MULTIPLE CHOICE OPTIONS
The primary purpose of a jib is:
To increase tip height
3 MULTIPLE CHOICE OPTIONS
When constructing crane mats, the best way to secure the timbers together is to:
Bolt them together
3 MULTIPLE CHOICE OPTIONS
When lifting a load out of water, you can expect:
The weight of the load to increase as the load displaces less water
3 MULTIPLE CHOICE OPTIONS
Unless otherwise noted by the manufacturer, lattice boom sections should be added:
With the shorter sections installed toward the butt end.
3 MULTIPLE CHOICE OPTIONS
The term “slew” means:
Swing
3 MULTIPLE CHOICE OPTIONS
Quadrants of operation can be found in:
Work area diagram
3 MULTIPLE CHOICE OPTIONS
Which of these functions could increase deflection of the crane’s boom?
Swinging the load
3 MULTIPLE CHOICE OPTIONS
Which of these statements is true?
Jib capacities increase as the angle to the ground increases
3 MULTIPLE CHOICE OPTIONS
Which of the following would be okay to remove from a carry deck crane for lifting operations?
Boom extension
3 MULTIPLE CHOICE OPTIONS
Which of these functions can change a mobile crane’s quadrant of operation?
Swing
3 MULTIPLE CHOICE OPTIONS
The angle between the legs of a 2-leg bridle hitch is referred to as the
Included angle
3 MULTIPLE CHOICE OPTIONS
OSHA refers to the area which it is reasonably foreseeable that partially or completely suspended materials could fall as the
Fall zone
3 MULTIPLE CHOICE OPTIONS
It’s okay to get under the crane’s boom during assembly/disassembly
When site constraints require it and A/D Director exercises precautions
2 MULTIPLE CHOICE OPTIONS
What is the purpose of a PTO?
To transfer power from the engine to the hydraulic pump
3 MULTIPLE CHOICE OPTIONS
Having an outrigger partially retracted
Makes the tipping axis closer to the crane’s center of gravity
3 MULTIPLE CHOICE OPTIONS
What is the purpose of an anemometer?
To measure wind speed.
3 MULTIPLE CHOICE OPTIONS
What device can be used to read boom length, radius and load weight?
Rated Capacity Indicator
3 MULTIPLE CHOICE OPTIONS
When severing wire rope in two to correct a localized deficiency in wire rope, what is not permitted?
Splicing
3 MULTIPLE CHOICE OPTIONS
Which of the following cannot be used to determine if the correct load chart is provided?
Date of manufacture
3 MULTIPLE CHOICE OPTIONS
When lifting a load on outriggers over which quadrant would yield the greatest ground pressure?
Over the Corner
3 MULTIPLE CHOICE OPTIONS
Who must confirm that powerlines are de-energized?
The Utilities Provider
3 MULTIPLE CHOICE OPTIONS
What indicates core damage in rotation resistant wire rope?
Localized loss of diameter
3 MULTIPLE CHOICE OPTIONS
List these three hitches in order from strongest to weakest.
Basket, Vertical, Choker
3 MULTIPLE CHOICE OPTIONS
When operating a mobile crane with a long boom, on uneven ground, what support condition should be considered?
Keeping a 90° angle between the stabilizer and the float
3 MULTIPLE CHOICE OPTIONS
Upon arrival at a job sit, the operator should first determine the condition of the:
Access roads
3 MULTIPLE CHOICE OPTIONS
On whose recommendations should a mobile crane preventative maintenance program be developed?
The Crane Manufacturer
3 MULTIPLE CHOICE OPTIONS
On the range diagram of a mobile crane, the boom length and boom angle can be used to determine?
The radius
3 MULTIPLE CHOICE OPTIONS
During a pick and carry the stability of the crane is based on what percentage of tipping?
75%
3 MULTIPLE CHOICE OPTIONS
When should a tag line be used, during the hoisting of material?
When rotation of the load can be considered hazardous
3 MULTIPLE CHOICE OPTIONS
Which of the following correctly states the requirements for hooks used to hoist employees on a crane-supported personnel platform?
Hooks shall have a latch that closes and locks
3 MULTIPLE CHOICE OPTIONS
What should be planned for in regards to getting a large crane to a job site?
Constricting roads
3 MULTIPLE CHOICE OPTIONS
While the operator is moving a suspended load, no employee must be within the fall zone, except for employees:
Operating a concrete hopper or concrete bucket
3 MULTIPLE CHOICE OPTIONS
ASME B30.5 lists the maximum allowable force required to operate hand levers on a crane as:
35 lbs.
3 MULTIPLE CHOICE OPTIONS
The cable on the top side of the boom is__________?
Not part of the load
3 MULTIPLE CHOICE OPTIONS
An audible signal device needs to be __?
In reach of the operator
3 MULTIPLE CHOICE OPTIONS
Which type of tagline is the least conductive?
Dry polypropylene
3 MULTIPLE CHOICE OPTIONS
When lifting over a corner, ground pressure generated by a crane can approach a weight that is:
Equal to the weight of the crane and the suspended load
3 MULTIPLE CHOICE OPTIONS