Non-masonry siding products such as wood, aluminum, vinyl, steel, and vinyl clad
siding are usually measured by the square foot, but the materials are typically sold
by the square (100 SF) or by the piece.
TrueFalse – ANSWER- True
Select the false statement.
Select the single best answer:
A. Vinyl clad siding is steel siding with a vinyl coating over it. It is more dentresistant than steel.
B. Vinyl siding is made of a rigid polyvinyl-chloride (PVC) compound. It is tough,
durable, and economical.
C. Aluminum siding has a baked-on enamel factory finished and can provide an
appearance closely resembling painted wood siding.
D. Vinyl clad siding is aluminum siding with a vinyl coating over it. It is more dent
resistant than aluminum and has less tendency to crack than vinyl.
E. Steel siding is more durable than vinyl, aluminum, or vinyl clad siding. Like
aluminum siding, it has a baked-on enamel factory finish. – ANSWER- Vinyl clad
siding is steel siding with a vinyl coating over it. It is more den-resistant than steel.
How many trusses (16″ o.c.) are in a 35′ 6″ long gable roof with no overhang on
the gable ends?
Select the single best answer:
A. 28
B. 27
C. 26
D. 29 – ANSWER- 28
According to the “Average Size Door Opening Guideline,” a missing wall
measuring 3’0″ wide x 6’8″ high would generally be subtracted from the quantity of
drywall needed for that room.
TrueFalse – ANSWER- False

A room is 15′ 3″ long, 13′ 5″ wide with a ceiling height of 8′, and the following
openings:
Patio door 6’0″ wide x 6’8″ high
Entry door 2’6″ wide x 6’8″ high
Window 1 5’0″ wide x 6’0″ high
Window 2 3’0″ wide x 6’0″ high
How many square feet (SF) of drywall are on the walls and ceiling?
Select the single best answer:
A. 388.70 SF
B. 458.72 SF
C. 593.36 SF
D. 588.75 SF – ANSWER- B. 458.72 SF
A room is 15′ 3″ long, 13′ 5″ wide with a ceiling height of 8′, and the following
openings:
Patio door 6’0″ wide x 6’8″ high
Entry door 2’6″ wide x 6’8″ high
Window 1 5’0″ wide x 6’0″ high
Window 2 3’0″ wide x 6’0″ high
How many LF of baseboard are in the room?
Select the single best answer:
A. 51.34 LF
B. 57.34 LF
C. 50.00 LF
D. 48.83 LF – ANSWER- A. 51.34 LF
In the Price List, the paint code, PNT P, does not allow for removal of switch and
outlet covers, dropping light fixtures or moving items away from walls.
TrueFalse – ANSWER- False
In the Price List, the price to remove and replace a turbine type roof vent is:
Select the single best answer:
A. $61.75
B. $60.39
C. $57.50
D. $66.95 – ANSWER- 66.95
In the Price List, the price to replace a roof mount power attic vent is:
Select the single best answer:
A. $206.35

B. $220.82
C. $217.66
D. None of the above. – ANSWER- 206.35
There is a 6″ x 6″ water stain on the acoustic ceiling (popcorn) texture of a 15′ x
15′ bedroom. The drywall and texture are undamaged. Which of the following best
describes the repair to the ceiling?
Select the single best answer:
A. PNT SP the entire bedroom ceiling.
B. PNT S (4 SF), then PNT P the entire bedroom ceiling.
C. PNT S (4 SF), then PNT AC the entire bedroom ceiling.
D. PNT ACS (2 SF), PNT ACP (6.25 SF) then PNT ACP the entire bedroom
ceiling. – ANSWER- PNT ACS (2 SF), PNT ACP (6.25 SF) the PNT ACP the
entire bedroom ceiling
In the Price List, the code to seal then paint the exterior is:
Select the single best answer:
A. PNT X2
B. PNT XS, then PNT X1
C. PNT XSP2
D. PNT XSP – ANSWER- C. PNT XSP
What is the category and selector code for a 3’0″ x 5’0″, single hung, vinyl window
with double glazing and heavy duty vinyl frame?
Select the single best answer:
A. WDV S+
B. WDV S>+
C. WDV S<+ D. WDV S> – ANSWER- WDVS>+
In the Price List, which of the following statements is true regarding the remove
unit price?
Select the single best answer:
A. It includes the labor to put the item in a container (truck, dumpster, etc.) within
a reasonable distance from the structure.
B. It includes labor to remove the item from the structure.
C. It includes the material cost of the item.
D. A and B only. – ANSWER- D