QUESTION
Decision Tree
Answer:
a graph of decisions and their possible conseque to create a plan to reach a goal
QUESTION
Expected Value
Answer:
-A weighted average of all possible outcomes with the weights being their probability of
occurring
-the SUM of all possible outcomes multiplied by their probability occurrence
-used in decision tree, payoff and expected values models

  • uses probabilty associated with different event outcomes
    -for each option, multiply each event by its associated probability
    -total up the SUM of the expected Value, select the options with the highest expected value
    QUESTION
    Expected Value Formula
    Answer:
    E = [x • P(x)]
    -multiply probabily times payoff, then add across the options such that probabilites add to 1 or
    100%

QUESTION
Example of Expected Value
Answer:
small building: strong sales are 10 million, weak sales are 2 million. Probability of strong sales
is .75, weak is .25
10*.75= 7.5 million, 2 million *.25= .5 million
7.5 +.5= 8 million
8 million is the expected value of the small building
QUESTION
Project Characteristics
Answer:

  • creates a unique product or service, or event
    -endeavor is outside of normal routine or operational activities
    -assignment is temporary
    -has a start and end date
    -contains tasks that are specific to the objective or goal of the project
    -all tasks must be done for it to be complete
    examples: completing a degree program, cooking a meal, building a house
    QUESTION
    Project Planning Activities
    Answer:
  • define the projects goals and objectives
    -define the tasks required to complete the project
    -define task dependencies and relationships )the order of tasks that they must be completed in)
    -define the duration (completion time), the completion costs, and required resources
    (labor, material, etc)
    -schedule, monitor, and control the project tasks as they are executed
    QUESTION
    Project Task

Answer:
-activity, is a unique unit of the project which can be described within limits of time
-sequence must be done to establish task dependencies
-each task must be assigned a duration, or length of time required to complete the task
QUESTION
Predecessor
Answer:
A task that must be completed before the next task can be started
QUESTION
Successor
Answer:
Task that must follow another task
QUESTION
Defining Project Tasks
Answer:

  • common practice to start in a tabular format, and cre- ate columns for important information
    (identifier, description, predecessor, duration, assigned resources, cost)
    -often start with the basic information (identifier, description) and add more informa- tion
    (predecessor, duration, costs…) as it becomes available
    QUESTION
    Project
    Answer:
    A strategic undertaking and not a regular operational activity
    QUESTION