Explain the reasons for incorporating dummy activities in a network diagram.

Explain the reasons for incorporating dummy activities in a network diagram. In what way do these differ from the normal activities?

Explain the basic logic of arrow networks.

How does the PERT technique help a business manager in decision-making?

The Correct Answer and Explanation is:

Reasons for Incorporating Dummy Activities in a Network Diagram

Dummy activities are used in Arrow Diagramming Method (ADM) or Activity-on-Arrow (AOA) network diagrams. They serve the following purposes:

  1. Maintain Logical Relationships: Dummy activities ensure the correct representation of precedence relationships between activities, especially when two activities share the same start and end events but are dependent on different predecessors.
  2. Avoid Ambiguity: Without dummy activities, it might appear that unrelated tasks are dependent on each other, leading to inaccurate scheduling and planning.
  3. Clarify Dependencies: They clarify which activity must be completed before another begins, even if it doesn’t require time or resources.
  4. Preserve Uniqueness: In AOA networks, each activity must have a unique representation; dummy activities help distinguish different relationships using zero duration arrows.

Difference from Normal Activities:

  • Duration: Dummy activities have zero duration, while normal activities consume time and resources.
  • Representation: Dummies are shown as dashed arrows, while normal activities use solid arrows.
  • Purpose: Dummy activities serve only to maintain logic; normal activities represent actual tasks or work.

Basic Logic of Arrow Networks

In Arrow Networks (AOA):

  • Arrows represent activities (tasks or jobs to be performed).
  • Nodes (circles) represent events (starting or ending points of activities).
  • Each activity is defined by its starting and ending event numbers.
  • The network flows left to right, showing the sequence of work.
  • The main goal is to identify the critical path, which determines the shortest time in which the project can be completed.

PERT Technique and Managerial Decision-Making

Program Evaluation and Review Technique (PERT) helps managers plan and control complex projects by analyzing tasks, durations, and dependencies.

How PERT Helps in Decision-Making:

  1. Time Estimates: PERT uses three estimates—optimistic (O), most likely (M), and pessimistic (P)—to compute an expected time (TE) using: TE=O+4M+P6TE = \frac{O + 4M + P}{6} This gives a more realistic timeline under uncertainty.
  2. Identifying Critical Path: Helps identify which sequence of tasks (critical path) directly impacts project completion. Managers can prioritize resources accordingly.
  3. Risk Management: By quantifying uncertainty, PERT helps in anticipating delays, adjusting plans, and minimizing risks.
  4. Better Resource Allocation: PERT allows forecasting resource needs and optimizing their use to avoid bottlenecks.
  5. Improved Communication: A visual timeline aids in coordination among teams and stakeholders.

In summary, PERT enables managers to plan efficiently, foresee potential issues, make informed scheduling decisions, and improve project success rates.