BU 345 Project Management Finals Exam (Qns & Ans) 2026
1. Which of the following is NOT a phase in the Project
Management Institute's (PMI) project management process
groups?
- A) Initiating
- B) Designing
- C) Executing
- D) Closing
Correct ANS: B) Designing
Rationale: The PMI framework includes five process
groups: Initiating, Planning, Executing, Monitoring &
Controlling, and Closing.
2. Which of the following is an example of a qualitative risk
analysis technique?
- A) Monte Carlo Simulation
- B) Risk Probability and Impact Matrix
- C) Expected Monetary Value Analysis
- D) Decision Tree Analysis
Correct ANS: B) Risk Probability and Impact Matrix
NUR 2356 Exam,NUR 2356 Test,NUR 2356 Flashcard,NUR 2356 quiz,NUR 2356 Practice,NUR 2356 Practice test,NUR 2356 Practice flashcard,NUR 2356 Practice exam,NUR 2356 Study guide,NUR 2356 Practice questions,NUR 2356 Questions,NUR 2356 Practice questions and answers,NUR 2356 Questions and answers,NUR 2356 pdf,NUR 2356 quizlet,NUR 2356 reddit,NUR 2356 Answer sheet,NUR 2356 Answer key,NUR 2356 Pdf free,NUR 2356 Exam help,NUR 2356 Cheat sheet,NUR 2356 quiz bank,NUR 2356 Questions bank,NUR 2356 Practice Guide,NUR 2356 Guide,NUR 2356 Testbank,NUR 2356 Practice Answers,NUR 2356 Answers,NUR 2356 Exam prep,NUR 2356 Prep,NUR 2356 Pdf download,NUR 2356 Flashcards,NUR 2356 Real questions,NUR 2356 Actual questions,NUR 2356 Real Questions and answers,NUR 2356 Actual Questions and answers,NUR 2356 Exam review,NUR 2356 Review,NUR 2356 Exam questions,NUR 2356 Exam questions and answers,NUR 2356 Practice test pdf,NUR 2356 Practice test quizlet,NUR 2356 Practice test Reddit,NUR 2356 Practice test quizlet multiple choice,NUR 2356 Exam study guide,NUR 2356 Practice test free,NUR 2356 Test questions,NUR 2356 Exam study guide,NUR 2356 Practice exam free,NUR 2356 Practice tests free,NUR 2356 Exam practice test,NUR 2356 Exam test questions,NUR 2356 Exam questions and answers,NUR 2356 Exam practice test