• wonderlic tests
  • EXAM REVIEW
  • NCCCO Examination
  • Summary
  • Class notes
  • QUESTIONS & ANSWERS
  • NCLEX EXAM
  • Exam (elaborations)
  • Study guide
  • Latest nclex materials
  • HESI EXAMS
  • EXAMS AND CERTIFICATIONS
  • HESI ENTRANCE EXAM
  • ATI EXAM
  • NR AND NUR Exams
  • Gizmos
  • PORTAGE LEARNING
  • Ihuman Case Study
  • LETRS
  • NURS EXAM
  • NSG Exam
  • Testbanks
  • Vsim
  • Latest WGU
  • AQA PAPERS AND MARK SCHEME
  • DMV
  • WGU EXAM
  • exam bundles
  • Study Material
  • Study Notes
  • Test Prep

CORRECT ANSWER : B - 100% Solved Question 1: Which of these document...

Class notes Dec 19, 2025
Preview Mode - Purchase to view full document
Loading...

Loading study material viewer...

Page 0 of 0

Document Text

  • | Page

CDT Exam Questions With CORRECT ANSWER s 100% Solved

Question 1: Which of these documents, might we find in the

Project Manual but they are not contract documents?(A) The Agreement (B) Procurement Documents (C) Addendum (D) Supplemental Conditions

CORRECT ANSWER : B

Reference: PDPG 11.1.6

Explanation: Procurement requirements are addressed to

prospective bidders or proposers interested in the project.Although not necessarily part of a contract, the procurement requirements are usually bound with other written construction documents into a project manual.

  • | Page

Question 2: Before a model building code can become the

building code for a jurisdiction, it has to be adopted by?(A) Authority Having Jurisdiction (B) State Government (C) Building Inspector (D) International Organization for Standardization

CORRECT ANSWER: A

Reference: PDPG 4.3

Explanation: Before a model building code can become the

building code for a jurisdiction, it has to be adopted by that AHJ. Once adopted, they then are responsible for enforcing that building code within their jurisdiction.

Question 3: The Construction Manager is hired by this entity?

(A) The General contractor (B) Owner

(C) A/E

  • | Page

(D) Contract Administrator

CORRECT ANSWER : B

Reference: PDPG 2.6.4

Explanation: The owner usually engages the services of a

construction manager, an entity that typically contracts with the owner to provide construction management services.

Question 4: The parties to the Construction Agreement are?

(A) General Contractor, Sub Contractor, and Construction Manager (B) A/E, General Contractor, and Contract Administrator (C) Building Official, and General contractor (D) Owner, Contractor, and A/E

CORRECT ANSWER : D

Reference: PDPG 7.2.3.1

  • | Page

Explanation: (PDPG Figure 5.1) The tripartite relationship

among the owner, contractor, and A/E is created by obligations to third parties to the contract. For example, the owner-A/E agreement may require certain duties of the A/E acting on behalf of the owner during construction. The contractor has a right to rely on the proper performance of these duties. The A/E, similarly, relies on the contractor to perform certain duties identified in the owner-contractor agreement, even though the A/E is not a party to that contract. The A/E relationship to the contractor in the owner-contractor agreement is a third-party relationship. These third-party relationships create the third side of the triangle in the construction process.(PDPG 7.2.3.1) The owner contracts first with the A/E to design the project and to prepare bidding documents. The owner then obtains bids through the competitive bidding process from bidding contractors. When one of he bidders is selected by the owner, the owner will either directly enter into the contract (such as for a project to be constructed with public funds), or negotiate the final cost and then enter into the contract (such as for a privately funded project).

Download Study Material

No purchase options are available for this study material at the moment.

Study Material Information

Category: Class notes
Description:

CDT Exam Questions With CORRECT ANSWER s 100% Solved Question 1: Which of these documents, might we find in the Project Manual but they are not contract documents? (A) The Agreement (B) Procurement...