-Guarantee passing score -55 Questions and Answers -format set of multiple-choice -Expert-Verified Explanation Question 1: Who signs caution/danger tags signifying that system status changes in installations of tags are compatible with ship and plant conditions
Answer:
Authorizing officer Question 2: On a 13 week report you annotate the check was fully accomplish using what symbol
Answer:
X
Question 3: What is an MRC
Answer:
Maintenance requirement card
Question 4: What program is used to create electronic tag outs
Answer:
MODES
Question 5: Who is the ships 3M manager
Answer:
Executive officer Question 6: Who is responsible for approving workcenter PMS schedules in sked 3.2
Answer:
DIVO
Question 7: Notes are associated with personal safety
Answer:
False Question 8: Who has overall responsibility for ensuring ships maintenance is accomplished IAW 3M procedures in the 3M system functions effectively with in the command
Answer:
Commanding officer
Question 9: And sked 3.2 who can assign maintenance responsibility
Answer:
WCS Question 10: What must happen if unsafe conditions are found while performing a maintenance requirement
Answer:
Report to the WCS
Question 11: Who is responsible for safety
Answer:
All hands Question 12: Which of the following is not a major element of the command in a NAVOSH program
Answer:
Food safety
Question 13: What is not contained on the workcenter LOEP
Answer:
Tools
Question 14: What does OMMA-NG stand for
Answer:
Organizational maintenance management system next generation
Question 15: What type of maintenance check is an R
Answer:
Situational requirement Question 16: What type of tag should be used to personal or equipment can be in Endangered while performing evolutions using normal operating procedure's
Answer:
Danger Question 17: What does the "S" in syscom control number "S 24 DWYG N" tell you
Answer:
Classified secret Question 18: What must you do as a maintenance person when unsafe conditions are found while performing PMS
Answer:
Notified the WCS Question 19: What are the duties and responsibilities of the second person on a equipment tag out procedures
Answer:
To act as a safety observer Question 20: How could you as a maintenance person know if you have scheduled maintenance
Answer:
Check the 13 week accountability log
Question 21: What is the purpose of CSMP
Answer:
To provide shipboard maintenance managers a list of conditions of the ship Question 22: What action should be taken first when a danger tagged components is found out of position
Answer:
Stop the work, report to WCS, report conditions to the authorizing officer Question 23: Lanyard locking what devices are acceptable for ideas locking devices for tag outs
Answer:
False Question 24: What symbol indicates mandatory maintenance is required and must be accomplished concurrently
Answer:
#
Question 25: Which form is used to change the supplemental information
Answer:
4790/2L
Question 26: What is the only section of an MRC that can be substituted by the workcenter supervisor
Answer:
Common hand tools
Question 27: What is ORM
Answer:
Operational risk management Question 28: Which of the following is an index of a complete set of MRC's applicable to a ship system, subsystem, or equipment
Answer:
MIP