PROJECT MANAGEMENT EXAM QUESTIONS
Actual Qs and Ans Expert-Verified Explanation
This Exam contains:
-Guarantee passing score -74 Questions and Answers -format set of multiple-choice -Expert-Verified Explanation Question 1: After defining project activities, the next step in project time management is developing the schedule
Answer:
False Question 2: maturity models, statistical methods, and test plans are examples of tools used in quality management
Answer:
true Question 3: The primary role of project stakeholder management is to ensure that the project will satisfy the stated needs for which it was undertaken
Answer:
true Question 4: it is much more expensive to make major changes to a project during earlier phases
Answer:
false
Question 5: an organizational culture with strong unit integration makes the project manager's job more difficult
Answer:
false Question 6: the arrows in a network diagram represent missed milestones in a project
Answer:
false Question 7: Using a systems approach is critical to successful project management
Answer:
true Question 8: the best way to sustain a project is to withhold the required money, human resources, and visibility for the project
Answer:
false Question 9: Critical chain scheduling assumes that resources multitask and maximizes multitasking
Answer:
false Question 10: It is important for the activity list and activity attributes to be in agreement with the work breakdown structure
Answer:
true Question 11: In a Gantt chart, thick black bars represent milestones achieved in a project
Answer:
false Question 12: It is mandatory for project managers working on large information technology projects to be experts in the field of information technology
Answer:
false
Question 13: according to a 2013 CHAOS study, user involvement is the most important factor that contributes to the success of IT projects
Answer:
false Question 14: Project managers should lead projects in isolation in order to truly serve the needs of the organization
Answer:
false Question 15: A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates
Answer:
true Question 16: Start-to-finish relationships are the most frequently used dependencies between activities
Answer:
false Question 17: Project schedules grow out of basic documents such as the project charter
Answer:
true Question 18: Knowing the amount of float allows project managers to know whether a project schedule is flexible
Answer:
true Question 19: a dependency pertains to the sequencing of project activities or tasks
Answer:
true
Question 20: In project time management, the next step after sequencing activities is to define these activities
Answer:
false Question 21: a drawback of the project management software is that it does not have the capacity to calculate the critical paths for a project
Answer:
false Question 22: Project managers in matrix organizations have staff from various functional areas working on their projects
Answer:
true Question 23: project managers must have cooperation from people in other parts of the organization
Answer:
true Question 24: the final process in project time management is developing the schedule
Answer:
false Question 25: A tracking Gantt chart is based on the percentage of work completed for project tasks for the actual start and finish dates
Answer:
true Question 26: One of PERT's main disadvantages is that it does not address the risk associated with duration estimates
Answer:
True