-Guarantee passing score -23 Questions and Answers -format set of multiple-choice -Expert-Verified Explanation Question 1: It is acceptable to open a locked door to let your boss in a building.
A) TRUE
B) FALSE
Answer:
B) FALSE
Question 2: Eating and drinking inside your vehicle while inside the plant is permitted.
A) TRUE
B) FALSE
Answer:
A) TRUE
Question 3: It is okay to start simple jobs without approved work permits.
A) TRUE
B) FALSE
Answer:
B) FALSE
Question 4: Requirements for conducting "Energized Electrical work" include:
- obtaining an energized work permit is approved by the site manager
- wearing arc flash PPE when working on electrical equipment 50 volts or above
- all of the above
Answer:
- all of the above
Question 5: Material may be removed from the solvay site without approval, as long as it results from demolition in connection with the contractors job.
A) TRUE
B) FALSE
Answer:
B) FALSE
Question 6: The taking of pictures without prior approval is acceptable, as long as the pictures are associated with the contract work.
A) TRUE
B) FALSE
Answer:
B) FALSE
Question 7: Personnel must keep at least one hand free to grasp a handrail, when climbing or descending steps.
A) TRUE
B) FALSE
Answer:
A) TRUE
Question 8: "Hot work" is defined as use of any equipment capable of producing a flame, spark, or heat.
A)TRUE
B) FALSE
Answer:
A) TRUE
Question 9: The anchorage point for fall protection system:
- can be any pipe or conduit
- must be a size 3" or larger pipe with all hangers in place and not above 200F, if pipe.
- can be any point on a roof truss
Answer:
- must be a size 3" or larger pipe with all hangers in place and not above 200F, if pipe.
- B2 Supervisor's Hallway
- B1 Vault
- B3 Locker Room
- All of the above
Question 10: In the event of a tornado warning, contractors shall assemble:
Answer:
- All of the above
Question 11: Loosening, but nit totally removing, the bolts of a pipe flange is considered "Line Entry"
A) TRUE
B) FALSE
Answer:
A) TRUE
Question 12: Incidents or unsafe conditions should be reported:
- immediately
- to your solvay site contract
- all of the above
Answer:
- all of the above
Question 13: A ground fault or circuit protector must be used if the outlet is not a ground fault outlet.
A) TRUE
B) FALSE
Answer:
A) TRUE
Question 14: Spills or releases must be reported to:
- your company foreman
- your site contract or any Solvay plant operations personnel
- the HSE coordinator
Answer:
- your site contract or any Solvay plant operations personnel
Question 15: In the event of an emergency evacuation, contractors shall assemble at the nearest staging point upwind of chemical vapors.