When submitting an emergency notification how many days does the state require for notice
before commencing any mold premeditation related activities? - Answer>>> Next Business Day
Define Mold Remediation - Answer>>> The removal, cleaning, sanitizing, demolition, or other
treatment including preventative activities, of mold contaminated matter that was not purposely
grown at a location.
What is a Mold Remediation Protocol? - Answer>>> Mold remediation work analysis - A
document prepared by a licensed mold assessment consultant for a client that specifies the
estimated quantities and locations of materials to be remediated and the proposed remediation
methods.
Not later than calendar days after the project stop-date, the MRC shall provide the property
owner with copies of required photographs of the scene of the mold remediation taken before
and after the remediation. - Answer>>> 7
Not later than calendar days after the project stop-date, the MRC shall provide the property
owner a Certificate of Mold Damage Remediation . - Answer>>> 10
Who needs to sign the Certificate of Mold Damage Remediation? - Answer>>> MRC and MAC
What 4 types of Toxigenic Mold species are known to produce mycotoxins? - Answer>>> 1.
Stachybotrys
2. Aspergillus
3. Penicillium
4. Fusarium
What are 3 common areas mold can be found? - Answer>>> 1. HVAC
2. Condensate Drain Pipe
3. Vapor Barriers
What are the 4 potential Health Effects of Mold? - Answer>>> 1. Allergic Reactions/Disease
2. Irritant Effects
3. Infection
4. Toxic Effects
What are 5 Irritant Effects Mold can have on the body? - Answer>>> 1. Eyes
2. Skin
3. Nose
4. Throat
5. Lungs