34) A document that outlines weights, crane configuration and
rigging requirements for a lift is called a: - ----Answers---Lift
plan
35) A 1-inch wire rope sling in vertical basket hitch lifting a 24- foot long, 36 inch diameter pipe, - ----Answers---36 to 1
36) What is an LMI? - ----Answers---Load movement indicator
37) Location of electrical hazards on the job site should be
documented on a: - ----Answers---Lift plan
38) When forming a lift plan, a PRIMARY concern for the
person doing the rigging is: - ----Answers---Capacity of
rigging
39) When using a wedge socket, the dead end of the rope is
secured in the socket by the: - ----Answers---Wedge
- / 2
40) When erecting or stowing a swing-away lattice extension, what should be used to control the movement of the extension? - ----Answers---Tag line
41) Planning for rigging is required: - ----Answers---Only
when lifting any load
42) A lift plan MUST be completed by a: - ----Answers---
Supervisor
43) Anchorage points for fall arrest harness for a single
person MUST be able to hold: - ----Answers---5000 lbs.
44) Which of the following items are used for heavy rigging? - ----Answers---Slings, shackles, and spreader beam
45) If the jacket of a synthetic round sling is damaged, that
sling should be: - ----Answers---Removed from service
immediately
46) Which of the following is NOT a factor when making submerged lifts? - ----Answers---Water temperature
47) When a tugger is mounted where the operator can NOT see the load, the signal person most uses - ----Answers--- Signals used for cranes