- What is the primary purpose of a building permit in Utah?
- To increase project cost
- To ensure compliance with building codes
- To guarantee contractor profit
- To prevent property taxes
- To ensure compliance with building codes
Rationale: Building permits are required to ensure that construction
meets local and state codes, promoting safety and compliance.
- According to Utah law, a contractor must provide a written contract
for any residential project over: 1 / 4
A. $500
B. $1,000
C. $2,500
D. $5,000
C. $2,500
Rationale: Utah requires written contracts for residential projects
exceeding $2,500 to protect both homeowner and contractor rights.
- Which of the following is considered an acceptable method for
- Posting “No Trespassing” signs only
- Installing fencing and lighting
- Leaving materials unlocked
- Informing neighbors verbally
- Installing fencing and lighting
protecting a construction site from unauthorized entry?
Rationale: Physical barriers and lighting are standard safety measures
to prevent theft and unauthorized access.
- What is the minimum slope required for a residential roof to ensure
- 1/4 inch per foot
- 1/2 inch per foot
- 1 inch per foot
- 2 inches per foot
- 1/2 inch per foot 2 / 4
proper drainage in Utah?
Rationale: Building codes require a minimum roof slope of 1/2 inch per
foot for water drainage and snow load management.
- When a contractor receives a deposit from a homeowner, Utah law
requires that the deposit must be:
- Returned only if work is delayed
- Applied to project costs
- Held in a trust or escrow account
- Spent at the contractor’s discretion
- Held in a trust or escrow account
Rationale: Utah law mandates that advance payments are protected
to ensure funds are used for the project and not misappropriated.
- Which type of insurance is mandatory for contractors in Utah?
- Life insurance
- Workers’ compensation
- Health insurance
- Auto insurance only
- Workers’ compensation
Rationale: Contractors with employees are required to carry workers’
compensation insurance to cover workplace injuries.
7. A change order should be used to:
- Decrease project cost without homeowner approval
- Document any modifications to the original contract
- Delay project completion 3 / 4
- Replace the original contract entirely
- Document any modifications to the original contract
Rationale: Change orders formalize adjustments to the scope of work,
timeline, or cost, ensuring legal protection.
- According to the Utah Residential Code, stair riser height must not
exceed:
- 6 inches
- 7 3/4 inches
- 8 1/2 inches
- 9 1/4 inches
- 7 3/4 inches
Rationale: The code sets maximum riser heights to reduce fall risk and
ensure uniformity.
9. The purpose of a vapor barrier in residential construction is to:
- Provide structural strength
- Prevent moisture from entering walls
- Reduce sound transmission
- Enhance paint adhesion
- Prevent moisture from entering walls
Rationale: Vapor barriers limit moisture infiltration that could lead to
mold, rot, and structural damage.
- When estimating materials for a concrete slab, the contractor
must consider: