NASCLA Contractors Guide Latest Update -
Questions and Verified Correct Answers Golden Ticket to Guaranteed A+ Verified by Professor
- CORRECT ANSWER:
Advantage of a Sole Proprietorship - CORRECT ANSWER: Freedom in decision-
making process
Allowances - CORRECT ANSWER: finish materials
change order
Americans with Disabilities Act (ADA) - CORRECT ANSWER: prohibits discrimination 15 or more employees
Architect and Owner's Representative - CORRECT ANSWER: The architect certify each progress payment
Bar Chart - CORRECT ANSWER: not show the interdependencies of activities
Bond - CORRECT ANSWER: is a risk transfer between a surety, the contractor, and
project owner
Budget and Cost Controls - CORRECT ANSWER: Less inventory onsite will also cut
down the risk of theft
Budget Tracking - CORRECT ANSWER: Job cost system
- / 2
Change Order - CORRECT ANSWER: a written agreement between the owner and
contractor to change the contract
Changes - CORRECT ANSWER: change of designated employee 90 days
change of a business/trade name 30 days change of address 30 days
Changes made after the contract is signed and executed are called - CORRECT
ANSWER: Modifications
Changes prior to the contract award are called - CORRECT ANSWER: Addenda
Class A
Class B - CORRECT ANSWER: $45,000
$15,000
Class A - CORRECT ANSWER: Single contract - $120,000 or more
12-month - $750,000 or more
Clean Water Act - CORRECT ANSWER: unlawful
discharge any pollutant into navigable waters, unless a National Pollutant Discharge Elimination System (NPDES) permit was obtained
Combine - CORRECT ANSWER: 7.65%
Commercial General Liability (CGL) - CORRECT ANSWER: bodily injury that results in actual physical damage or loss for individuals who are not employees.damage or loss to property not belonging to the business.