The 1970s law that set into place the regulation of stormwater is - correct answer- The clean water act
Requirements for managing stormwater activity on a construction site are outlined in the following regulation - correct answer- NPDES
Which of the following is never an allowable stormwater discharge from a construction site - correct answer- Discharge from contaminated ground water
The notice of termination can be filed when - correct answer- All construction activity, inside and outside of the building, is complete and permanent stabilization has been verified as adequate to meet permit requirements
- / 2
- | Page
Relative to stormwater permitting all of the following must occur before construction starts except - correct answer- Submit the notice of termination (NOT)
The stormwater notice of intent (NOI) must be submitted - correct answer- After the SWPPP is prepared and before starting construction
Potential pollutant sources stored on a construction site may include - correct answer- 1. Petroleum storage tanks
- Soil sediments
- Masonary material
4. ALL OF THE ABOVE
The SWPPP inflammation sequence may be modified - correct answer- After consulting with the project SWPPP Designer (CEC) and, if required, the project owner and receiving written approval
A SWPPP site map will show all of the following except - correct answer- Notices of violation