• wonderlic tests
  • EXAM REVIEW
  • NCCCO Examination
  • Summary
  • Class notes
  • QUESTIONS & ANSWERS
  • NCLEX EXAM
  • Exam (elaborations)
  • Study guide
  • Latest nclex materials
  • HESI EXAMS
  • EXAMS AND CERTIFICATIONS
  • HESI ENTRANCE EXAM
  • ATI EXAM
  • NR AND NUR Exams
  • Gizmos
  • PORTAGE LEARNING
  • Ihuman Case Study
  • LETRS
  • NURS EXAM
  • NSG Exam
  • Testbanks
  • Vsim
  • Latest WGU
  • AQA PAPERS AND MARK SCHEME
  • DMV
  • WGU EXAM
  • exam bundles
  • Study Material
  • Study Notes
  • Test Prep

Exam Practice 100 Questions And Correct

Class notes Jan 1, 2026 ★★★★☆ (4.0/5)
Loading...

Loading document viewer...

Page 0 of 0

Document Text

Certified Construction Manager (CCM) Exam Practice 100 Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf

  • Which document defines the scope, schedule, and budget of a
  • construction project?

  • Change Order
  • Project Management Plan
  • Submittal Log
  • Bid Proposal

Rationale: The Project Management Plan outlines the scope,

schedule, and budget, serving as the primary guide for project execution.

  • The primary role of a construction manager during the pre-

construction phase is to:

  • Perform structural inspections 1 / 4
  • Develop cost estimates and schedules
  • Approve shop drawings
  • Issue building permits

Rationale: Pre-construction focuses on planning, including cost

estimating, scheduling, and value engineering.

  • Which type of contract places the greatest risk on the owner?
  • Lump Sum
  • Cost-Plus-Fee
  • Fixed-Price
  • Unit Price

Rationale: In a Cost-Plus-Fee contract, the owner assumes cost

overruns, while the contractor is reimbursed for actual costs plus a fee.

4. A critical path in a schedule is:

  • The path with the most resources assigned
  • The sequence of tasks that determines the shortest project
  • duration

  • The longest list of non-critical tasks
  • Any path that is delayed

Rationale: The critical path identifies tasks that directly affect project

completion; delays on this path delay the project.

5. The most effective method to control project quality is to:

  • Rely on subcontractor quality 2 / 4
  • Conduct inspections at the end of the project
  • Implement quality assurance and quality control procedures
  • throughout the project

  • Only review final deliverables

Rationale: Quality management requires continuous monitoring and

verification during construction, not just at the end.

  • Which insurance covers damages to the project site caused by the
  • contractor?

  • Professional Liability
  • Workers Compensation
  • Builder’s Risk Insurance
  • General Liability

Rationale: Builder’s Risk Insurance covers physical loss or damage to

a construction project while it is in progress.

7. In risk management, a contingency reserve is primarily used to:

  • Pay contractor salaries
  • Address unknown risks
  • Fund design changes
  • Reduce insurance premiums

Rationale: Contingency reserves are set aside to manage unforeseen

events or uncertainties.

8. Value engineering is best applied during:

  • Project closeout 3 / 4
  • Construction only
  • Design development and pre-construction
  • Subcontractor bidding

Rationale: Value engineering seeks cost efficiency and function

optimization, ideally before construction begins.

9. The primary purpose of a change order is to:

  • Terminate a contract
  • Modify the contract scope, schedule, or price
  • Update insurance requirements
  • Reassign subcontractors

Rationale: Change orders formally adjust contract terms, such as

cost, scope, or schedule.

  • Which of the following best describes a Guaranteed Maximum
  • Price (GMP) contract?

  • Owner pays actual costs plus a fixed fee
  • Contractor assumes risk for costs exceeding the maximum price
  • Contractor is paid per unit installed
  • Owner bears all cost overruns

Rationale: In a GMP, the contractor guarantees the project will not

exceed a set price, transferring some cost risk to the contractor.

  • The main advantage of using Building Information Modeling

(BIM) is:

  • Reduces labor costs automatically
  • / 4

User Reviews

★★★★☆ (4.0/5 based on 1 reviews)
Login to Review
S
Student
May 21, 2025
★★★★☆

This document provided step-by-step guides, which made learning easy. Absolutely impressive!

Download Document

Buy This Document

$1.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Class notes
Added: Jan 1, 2026
Description:

Certified Construction Manager (CCM) Exam Practice 100 Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf 1. Which document defines the scope, schedule...

Unlock Now
$ 1.00