Certified Construction Manager (CCM) Exam Practice 100 Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which document defines the scope, schedule, and budget of a
- Change Order
- Project Management Plan
- Submittal Log
- Bid Proposal
construction project?
Rationale: The Project Management Plan outlines the scope,
schedule, and budget, serving as the primary guide for project execution.
- The primary role of a construction manager during the pre-
construction phase is to:
- Perform structural inspections 1 / 4
- Develop cost estimates and schedules
- Approve shop drawings
- Issue building permits
Rationale: Pre-construction focuses on planning, including cost
estimating, scheduling, and value engineering.
- Which type of contract places the greatest risk on the owner?
- Lump Sum
- Cost-Plus-Fee
- Fixed-Price
- Unit Price
Rationale: In a Cost-Plus-Fee contract, the owner assumes cost
overruns, while the contractor is reimbursed for actual costs plus a fee.
4. A critical path in a schedule is:
- The path with the most resources assigned
- The sequence of tasks that determines the shortest project
- The longest list of non-critical tasks
- Any path that is delayed
duration
Rationale: The critical path identifies tasks that directly affect project
completion; delays on this path delay the project.
5. The most effective method to control project quality is to:
- Rely on subcontractor quality 2 / 4
- Conduct inspections at the end of the project
- Implement quality assurance and quality control procedures
- Only review final deliverables
throughout the project
Rationale: Quality management requires continuous monitoring and
verification during construction, not just at the end.
- Which insurance covers damages to the project site caused by the
- Professional Liability
- Workers Compensation
- Builder’s Risk Insurance
- General Liability
contractor?
Rationale: Builder’s Risk Insurance covers physical loss or damage to
a construction project while it is in progress.
7. In risk management, a contingency reserve is primarily used to:
- Pay contractor salaries
- Address unknown risks
- Fund design changes
- Reduce insurance premiums
Rationale: Contingency reserves are set aside to manage unforeseen
events or uncertainties.
8. Value engineering is best applied during:
- Project closeout 3 / 4
- Construction only
- Design development and pre-construction
- Subcontractor bidding
Rationale: Value engineering seeks cost efficiency and function
optimization, ideally before construction begins.
9. The primary purpose of a change order is to:
- Terminate a contract
- Modify the contract scope, schedule, or price
- Update insurance requirements
- Reassign subcontractors
Rationale: Change orders formally adjust contract terms, such as
cost, scope, or schedule.
- Which of the following best describes a Guaranteed Maximum
- Owner pays actual costs plus a fixed fee
- Contractor assumes risk for costs exceeding the maximum price
- Contractor is paid per unit installed
- Owner bears all cost overruns
Price (GMP) contract?
Rationale: In a GMP, the contractor guarantees the project will not
exceed a set price, transferring some cost risk to the contractor.
- The main advantage of using Building Information Modeling
(BIM) is:
- Reduces labor costs automatically
- / 4