CONTRACTOR EXAM PRACTICE

QUESTIONS AND CORRECT ANSWERS

(VERIFIED ANSWERS)

  • Which of the following best describes the primary purpose of a
  • performance bond?

  • To guarantee the contractor’s profit
  • To guarantee the project’s timely completion
  • To guarantee the contractor will complete the project according
  • to the contract

  • To guarantee subcontractors will be paid

Correct Answer: C) To guarantee the contractor will complete the

project according to the contract. (Rationale: A performance bond

ensures the contractor fulfills the contract obligations and completes the project as specified.)

  • What is the maximum amount a contractor may retain from a
  • subcontractor’s payment in Florida without a written agreement?

  • 5%

B) 10%

C) 15%

  • | P a g e
  • 0%
  • Correct Answer: D) 0%. (Rationale: Florida law prohibits a contractor from withholding payment from a subcontractor unless there is a written agreement stating otherwise.)

  • Which document officially establishes the legal responsibilities
  • and scope of work for a construction project?

  • Invoice
  • Contract
  • Purchase order
  • Change order
  • Correct Answer: B) Contract. (Rationale: The contract defines the scope, responsibilities, and legal obligations of all parties.)

  • Under Florida law, which type of insurance is required for all
  • licensed contractors?

  • Life insurance
  • Workers’ compensation insurance
  • Health insurance
  • Professional liability insurance
  • Correct Answer: B) Workers’ compensation insurance. (Rationale: Contractors with employees must maintain workers’ compensation insurance as required by Florida Statutes.)

  • | P a g e
  • When must a notice to owner (NTO) be served to preserve lien
  • rights in Florida?

  • Before the first delivery of materials
  • Within 45 days of first furnishing labor or materials
  • Within 90 days after project completion
  • Within 30 days after contract signing

Correct Answer: B) Within 45 days of first furnishing labor or

materials. (Rationale: Florida law requires serving an NTO within 45

days of starting work or providing materials to protect lien rights.)

  • Which of the following is considered a general condition cost?
  • Lumber
  • Nails
  • Project superintendent’s salary
  • Concrete
  • Correct Answer: C) Project superintendent’s salary. (Rationale: General condition costs include salaries of on-site management and indirect project expenses.)

7. The term “retainage” refers to:

  • Contractor’s profit
  • Tax withheld from the project
  • A portion of payment withheld until project completion
  • Subcontractor fees
  • | P a g e

Correct Answer: C) A portion of payment withheld until project

completion. (Rationale: Retainage is money withheld to ensure the

contractor completes the work satisfactorily.)

  • What is the minimum clear width for an accessible door according
  • to Florida Accessibility Code?

  • 28 inches
  • 30 inches
  • 32 inches
  • 36 inches
  • Correct Answer: C) 32 inches. (Rationale: The Florida Accessibility Code requires doors to provide a minimum clear opening of 32 inches for accessibility.)

  • Which of the following is the best way to prevent soil erosion on a
  • construction site?

  • Using sandbags only
  • Removing all vegetation
  • Installing silt fences and sediment control measures
  • Paving all soil areas

Correct Answer: C) Installing silt fences and sediment control

measures. (Rationale: Silt fences and other sediment control

measures prevent erosion and sediment from leaving the site.)

User Reviews

★★★★☆ (4.0/5 based on 1 reviews)
Login to Review
S
Student
May 21, 2025
★★★★☆

With its detailed explanations, this document made learning easy. Definitely a outstanding choice!

Download Document

Buy This Document

$30.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: EXAMS AND CERTIFICATIONS
Added: Aug 31, 2026
Description:

FLORIDA CERTIFIED GENERAL CONTRACTOR EXAM PRACTICE QUESTIONS AND CORRECT ANSWERS (VERIFIED ANSWERS) 1. Which of the following best describes the primary purpose of a performance bond? A) To guarant...

Unlock Now
$ 30.00