After three iterations of crashing, how many paths are now critical? What additional activities are now critical as a result of the crashing?
a.Two paths | Activities B and D are now critical as a result of the crashing.b.One path | Activities A and G are now critical as a result of the crashing.c.Five paths | Activities A and G are now critical as a result of the crashing.d.Three paths Activities A and G are now critical as a result of the crashing.e.Four paths | Activities B and E are now critical as a result of the crashing.
THIS - ----Answers___e. 1 / 4
Four paths | Activities B and E are now critical as a result of the crashing.
Suppose indirect costs are $2,000/day and that your primary objective was to reduce costs through crashing along with reduction in duration. How many days would you crash the project? How many iterations would this take?
a.Fourteen days | Three iterations b.Three days | Three iterations c.Thirteen days | Two iterations d.Twelve days | Two iterations e.Four days | Three iterations
THIS - ----Answers___a.Fourteen days | Three iterations
The traits of successful project managers include all of the following except ________.
- 2 / 4
all of these are traits of successful project managers b.effective time management c.effective communication skills d.proactivity e.personal integrity
THIS - ----Answers___a.all of these are traits of successful project managers
Research consistently points out that project success is strongly affected by the degree to which a project has the support of top management. The following are ways a project manager can manage upward relationships except ________.
a.consistently follow through on requests b.prove loyalty c.pick the optimum time to appeal to top management
- 3 / 4
accept profound differences in perspective and become skilled at the art of persuading superiors e.demonstrate that you have character and competence
THIS - ----Answers___e.demonstrate that you have character and competence
Which of the following is not a competence for the project manager?
a.Be a good communicator b.Be a good delegator c.Be a good motivator d.Be a good mentor e.Be a good developer/coder - ----Answers___e.Be a good developer/coder
According to Frederick Hertzberg, which of the following is not a motivational factor?
- / 4