District of Columbia General Contractor Licensing Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
Q1: Which type of insurance is legally required for contractors in the District
of Columbia to protect workers from job-related injuries?
- Property Insurance
- General Liability Insurance
- Workers’ Compensation Insurance
- Professional Liability Insurance
Rationale: Workers’ Compensation Insurance is mandatory to cover
medical expenses and lost wages for employees injured on the job.
- / 4
Q2: What is the primary purpose of a building permit in the District of
Columbia?
- To increase property taxes
- To ensure construction complies with local codes
- To guarantee construction quality
- To provide insurance coverage
Rationale: A building permit ensures that all construction work meets DC’s
building codes and safety standards.
Q3: Which of the following is a valid reason for the Department of
Consumer and Regulatory Affairs (DCRA) to revoke a contractor license?
- Late payment of workers
- Fraud or misrepresentation in license application
- Choosing a subcontractor
- Filing taxes late
Rationale: Fraudulent activity or misrepresentation during the licensing
process is grounds for revocation.
Q4: What is the maximum period a general contractor in DC can hold a
permit without starting work before expiration?
- 3 months
- 6 months 2 / 4
- 12 months
- 24 months
Rationale: Permits typically expire after 12 months if work has not
commenced, unless an extension is granted.
Q5: In DC, which document governs contractor obligations related to
occupational safety?
- DC Real Estate Code
- Occupational Safety and Health Act (OSHA)
- DC Tax Code
- National Fire Code
Rationale: OSHA regulations define workplace safety requirements for
contractors and employees.
Q6: When is a contractor required to provide a written contract for
construction work in DC?
- Only for projects over $10,000
- For any project over $500
- Only for residential projects
- Only for commercial projects
Rationale: DC law mandates written contracts for construction projects
exceeding $500 to protect both parties. 3 / 4
Q7: What type of bond is often required for public construction projects in
DC?
- Performance bond
- Payment bond
- Both performance and payment bonds
- Bid bond only
Rationale: Public projects generally require both performance bonds (to
guarantee completion) and payment bonds (to ensure subcontractors and suppliers are paid).
Q8: Which of the following best describes a “change order”?
- A new construction permit
- A written modification to the original contract
- A contractor’s license application
- A payroll record
Rationale: A change order documents any modifications to scope, cost, or
schedule of an existing contract.
Q9: What is the primary purpose of a lien waiver in construction?
- To increase profit margins
- To extend project deadlines
- / 4