MGMT 5220 FINAL EXAM (ACTUAL / ) LATEST
QUESTIONS WITH VERIFIED CORRECT ANSWERS GRADE A+
scheduling variance provides a comparison between planned and actual performance but does not include actual costs
cost variance compares deviations only from the budget and doesn't provide a measure of comparison between work scheduled and work accomplished.
50/50 rule Assigns half completed as soon as an activity is started & 100% when an activity is finished.
• comes from SMEs
0/100 rule 1 / 4
• Project activity has a value of $0 until the activity is finished then value of 100% of the budget
• Works well for short duration activities(couple of days)
Project-driven organization reporting internals happen...weekly
Non-project-driven organization reporting internals happen...monthly
Progress reporting needs to answer four fundamental
questions:
- Where are we today (time and cost)?
- Where will we end up (time and cost)?
- What are the present and future risks?
4. Variance analysis: Are there any special problems that need
to be addressed and what can management do to help? 2 / 4
Management Reserve • An amount of the project budget withheld for management control purposes. (for unforeseen work) contingency fund
• not included in the performance measurement baseline
(PMB).
Lags the logical relationship between the start and finish of one activity and the start and finish of another activity
• allow for flexibility
Examples of lag Let cement dry, let computer run, travel time
Lag is NOT part of the activity, as there is no ___ involved 3 / 4
labor
Most common type of sequencing finish to start lag
Finish to Start lag requires the current activity to be finished before its successor can start.
- most common
- not the same as activity slack
Finish to Finish Lag • 2 tasks share a similar completion point
• the finish of the successor task is dependent on the finish of the predecessor task
Start to Start Lag
- / 4