• wonderlic tests
  • EXAM REVIEW
  • NCCCO Examination
  • Summary
  • Class notes
  • QUESTIONS & ANSWERS
  • NCLEX EXAM
  • Exam (elaborations)
  • Study guide
  • Latest nclex materials
  • HESI EXAMS
  • EXAMS AND CERTIFICATIONS
  • HESI ENTRANCE EXAM
  • ATI EXAM
  • NR AND NUR Exams
  • Gizmos
  • PORTAGE LEARNING
  • Ihuman Case Study
  • LETRS
  • NURS EXAM
  • NSG Exam
  • Testbanks
  • Vsim
  • Latest WGU
  • AQA PAPERS AND MARK SCHEME
  • DMV
  • WGU EXAM
  • exam bundles
  • Study Material
  • Study Notes
  • Test Prep

NERC EXAM WITH 200 QUESTIONS AND

Exam (elaborations) Dec 14, 2025 ★★★★★ (5.0/5)
Loading...

Loading document viewer...

Page 0 of 0

Document Text

NERC EXAM WITH 200 QUESTIONS AND

CORRECT ANSWERS/ NERC ACTUAL -

LATEST REAL EXAM QUESTIONS AND ALL

CORRECT ANSWERS (BRAND NEW!!)

  • According to NERC standards, disturbances that are not identified until
  • sometime after the occur must be reported to NERC

  • Immediately
  • Within 12 hours
  • Within 24 hours
  • Within 30 days - ANSWER-c. Within 24 hours
  • If a 500 kV transmission line with a surge impedance loading of 800 MW is
  • currently loaded at 1400 MW, which of the following events would most likely occur?

  • Generator MVAR output would increase
  • All system capacitors would trip off-line
  • Generator MVAR output would decrease
  • All automatic reactors would connect to the system - ANSWER-a. Generator
  • MVAR output would increase

  • If your transmission path is rated for 1200 MW and 1000 MW are scheduled on
  • it, but due to parallel flows the actual flow is 1300 MW, what action should you take? 1 / 4

  • Request that a phase shifting transformer be installed
  • Reduce interchange transactions impacting the path
  • Request all parallel flow to PSEs to increase schedules
  • Reduce all commercial customer load - ANSWER-b. Reduce interchange
  • transactions impacting the path

  • According to NERC Standards, Transmission Operators and Balancing
  • Authorities must provide their operating personnel with a minimum of how much training annually?

  • 2 days
  • 5 days
  • 10 days
  • 14 days - ANSWER-b. 5 days
  • Which of the following actions can a system operator take in order to maintain
  • stability on the system?

  • Request generators to absorb maximum MVAR
  • Place all operating limits on dynamic calculation
  • Raise system voltages as high as possible, but within their operating parameters
  • Reduce voltages on the transmission system - ANSWER-c. Raise system
  • voltages as high as possible, but within their operating parameters

  • Which of the following actions should you take if an outage on a neighboring
  • system has caused a violation on your system? 2 / 4

  • Open all tie-lines to your neighbor
  • Ask the Reliability Coordinator for assistance
  • Shed load to mitigate the violation
  • Wait for the neighboring system to contact you - ANSWER-b. Ask the
  • Reliability Coordinator for assistance

  • If a SOL or IROL violation occurs due to transfers across the system and it is
  • determined that parallel flows are contributing to the violation, what should the system operator do?

  • Place all system capacitors in service
  • Reduce system load
  • Inform the Reliability Coordinator
  • Dump firm load - ANSWER-c. Inform the Reliability Coordinator
  • While performing a pre-outage study, you identify that the transmission outage
  • will cause a thermal violation on a parallel path, which of the following actions would be the first one you would implement?

  • Shed load to mitigate the concern
  • Allow the outage to occur and see what happens
  • Reschedule the outage if possible
  • Allow the outage to take place as long as no load is lost - ANSWER-c.
  • Reschedule the outage if possible

  • Which of the following actions should the system operator implement first if
  • transmission line limits exceed the facilities emergency limits based on a 3 / 4

contingency that has not yet occurred, but their protocols are to respond on a pre- contingency basis?

  • Reduce voltages in the area of the violation
  • Remove the facility from service
  • Curtail any interchange transactions that are curtailable
  • Only implement actions if the contingency occurs - ANSWER-c. Curtail any
  • interchange transactions that are curtailable

  • If a Reliability Coordinator had to implement any type of line loading relief
  • procedures, which of the following entities would they be coordinated with? Pick two.

  • Purchasing Selling Entities
  • Balancing Authorities
  • Transmission Operators
  • Load Serving Entities - ANSWER-b. Balancing Authorities
  • Transmission Operators
  • If a generator is lost in a neighboring Balancing Area, what would the impact
  • be on the BAs transmission tie lines?

  • Nothing
  • A net increase of MW would come into your BAs system
  • A net increase of MW would go out of your BAs system
  • They would exceed their emergency limits - ANSWER-c. A net increase of MW
  • would go out of your BAs system

  • / 4

User Reviews

★★★★★ (5.0/5 based on 1 reviews)
Login to Review
S
Student
May 21, 2025
★★★★★

With its in-depth analysis, this document made learning easy. Definitely a outstanding choice!

Download Document

Buy This Document

$1.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Exam (elaborations)
Added: Dec 14, 2025
Description:

NERC EXAM WITH 200 QUESTIONS AND CORRECT ANSWERS/ NERC ACTUAL - LATEST REAL EXAM QUESTIONS AND ALL CORRECT ANSWERS (BRAND NEW!!) 1. According to NERC standards, disturbances that are not identified...

Unlock Now
$ 1.00