• wonderlic tests
  • EXAM REVIEW
  • NCCCO Examination
  • Summary
  • Class notes
  • QUESTIONS & ANSWERS
  • NCLEX EXAM
  • Exam (elaborations)
  • Study guide
  • Latest nclex materials
  • HESI EXAMS
  • EXAMS AND CERTIFICATIONS
  • HESI ENTRANCE EXAM
  • ATI EXAM
  • NR AND NUR Exams
  • Gizmos
  • PORTAGE LEARNING
  • Ihuman Case Study
  • LETRS
  • NURS EXAM
  • NSG Exam
  • Testbanks
  • Vsim
  • Latest WGU
  • AQA PAPERS AND MARK SCHEME
  • DMV
  • WGU EXAM
  • exam bundles
  • Study Material
  • Study Notes
  • Test Prep

NERC Test Questions Latest Update -

Exam (elaborations) Dec 14, 2025 ★★★★★ (5.0/5)
Loading...

Loading document viewer...

Page 0 of 0

Document Text

NERC Test Questions Latest Update - 225 Questions and 100% Verified Correct Answers Actual Exam Guaranteed A+

A Reliability Adjustment Arranged Interchange must be approved by who? - CORRECT

ANSWER: Only the source and sink, the key word to remember is Adjustment

A TO must coordinate its load shedding plans, excluding UFLS, with who? - CORRECT

ANSWER: Other interconnected TO and BA

According to EOP-002, what actions are acceptable in an operating capacity or energy

emergency by a BA? - CORRECT ANSWER: Bringing on all available generation,

postponing equipment maintenance, scheduling interchange purchases, and reduce firm load

According to NERC, where should voltage be maintained during restoration? -

CORRECT ANSWER: 90 to 110 percent of Nominal

After a system modification is made, how long does the TO have to update restoration

plans? - CORRECT ANSWER: 90 days

After how long does a complete loss of monitoring capability meet reporting threshold? -

CORRECT ANSWER: 30 minutes

After how long must a complete loss of voice communications be reported? -

CORRECT ANSWER: 30 minutes

An RC backup control facility is not required to be available during what two conditions?

- CORRECT ANSWER: Planned outages of two weeks or less; unplanned outages

  • / 3

BA and RC are given responsibility and authority to make decisions to alleviate what? -

CORRECT ANSWER: Capacity and energy emergencies

BA not serving native load minimum frequency bias is based on... - CORRECT

ANSWER: The montlhly average Frequency Bias is at least 1 % of the BA estimated

yearly peak generation per .1 Hz (Load = 1 % demand; No Load = 1 % Gen)

BA serving native load minimum frequency bias is based on... - CORRECT ANSWER:

The monthly average Frequency Bias is at least 1% of the BA estimated yearly peak demand per .1 Hz (Load = 1 % demand; No Load = 1 % Gen)

By what means does an RC notify other RCs of a declared EEA? - CORRECT

ANSWER: The RCIS - Reliability Coordinator Information System

Describe Attachment 1 and attachment 2 of EOP-004 Event Reporting: - CORRECT

ANSWER: Att 1 is the events required to be reported; Att 2 is the Event Reporting Form

During an EEA 2 what must BA and market participants with resources do to help? -

CORRECT ANSWER: Immediately contact the Energy Deficient Entity

Each BA and RC shall have the ____ and clear decision-making ____ to take whatever actions are needed to ensure reliability of its respective area... - CORRECT ANSWER: responsibility and authority

Each BA must report its Bias Setting and the method for determining it to which entity? -

CORRECT ANSWER: NERC Operating Committee

Emergency plans are made for what three conditions? - CORRECT ANSWER:

Generating Capacity loss, Transmission System loss, Load Shedding plans

Events meeting event report threshold: - CORRECT ANSWER: Damage, destruction or physical threats physical threats to a facility, physical threats to a control center, public appeal for load reduction, system-wide voltage reduction >3%, manual or automatic firm 2 / 3

load shedding >100MW; voltage deviation +/- 10% for 15 minutes; IROL or SOL violation, loss of Firm load, System separation (islanding), generation loss, complete loss of offsite power to a nuclear plant, transmission loss, control center evacuation, complete loss of voice comm or monitoring capabilities

Following a Contingency or other event that results in an IROL violation, how long does

the TO have to bring the system back into limits? - CORRECT ANSWER: As soon as

possible and not to exceed 30 minutes

For how long must a BES control center be evacuated to meet the event reporting

requirement? - CORRECT ANSWER: 30 minutes

Frequency Bias needs to be as close as practical to or _______ than the BA Frequency

Response. - CORRECT ANSWER: Bias setting must be equal to or GREATER than the

frequency response

Geo magnetic disturbances induce what type of current? - CORRECT ANSWER: Large

amounts of low frequency current that can enter the system through grounds and cause equipment damage, namely to transformers

How can an EEA be initiated? - CORRECT ANSWER: Only by an RC at the RCs own

request, upon request of a BA or upon request of a LSE

How do we know comms will be good? - CORRECT ANSWER: They will manage,

alarm, test and/or actively monitor, especially emergency comm facilities and equipment (non-routine equipment)

How does a BA account for the Frequency Bias of a shared unit? - CORRECT ANSWER: Each BA will account for their portion of the governor droop response in their Bias Setting

How does BA include remote BA, jointly owned generation in its ACE? - CORRECT ANSWER: Using dynamic schedule and pseudo ties for its ACE, reflecting its respective share of the unit governor droop response in their Hz Bias.

  • / 3

User Reviews

★★★★★ (5.0/5 based on 1 reviews)
Login to Review
S
Student
May 21, 2025
★★★★★

This document provided detailed explanations, which made learning easy. Absolutely impressive!

Download Document

Buy This Document

$1.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: Exam (elaborations)
Added: Dec 14, 2025
Description:

NERC Test Questions Latest Update - 225 Questions and 100% Verified Correct Answers Actual Exam Guaranteed A+ A Reliability Adjustment Arranged Interchange must be approved by who? - CORRECT ANSWER...

Unlock Now
$ 1.00