NJDEP UST TRAINING FOR CLASS A&B OPERATORS (ACTUAL
EXAM QUESTIONS AND VERIFIED CORRECT
ANSWERS
A class B operator shall not be responsible for more than the
following facilities:
45 facilities
What is the minimum frequency of site inspections to assure operational compliance?Quarterly
If a facility has been determined by the DEQ inspector to be out of compliance with the significant operational compliance
requirements, the DEQ shall retrain:
The class A operator of the facility.
When planning to permanently close an UST system, the DEQ
must be notified not less than the following days:
30 days
Upon permanent removal of an UST system, the operator shall: 1 / 2
Notify the DEQ within 30 days with an amended registration form.
The operator shall notify the DEQ of a confirmed release upon
removal of an UST and visual evidence showing:
Either B or C: B. There is visibly contaminated groundwater in
the tank cavity.
- There is visibly contaminated soil in the tank cavity and/or
soil removed from the tank cavity.
Upon removal of an UST where there is no visual or olfactory
evidence of a release, the operator shall:
Take soil samples, analyze them, and then send the site assessment results to the DEQ for a determination.
A leak should be suspected in a 1,560-gallon tank if the variation between the beginning and ending manual tank gauging liquid level measurements exceeds the weekly
standard of X gallons. X is:
26 gallons
The Class B operator should inspect the UST system for
operational compliance status at a minimum:
- / 2