Contents Project management evaluation and reflection 3 Time planning and schedule 3 Evaluating Gantt chart 4 Budget 6 Adherence to the project methodology 10 RAD methodology 10 Waterfall methodology 12 Improvements that could be made to the project management skills and behaviours applied during this project 14 Release Form 15 Document 15 Signed document 16
- / 2
Project management evaluation and reflection
Time planning and schedule
Overall, this project can be considered a success in terms of time scheduling as it was ultimately completed on schedule - that also includes this section of evaluating the project management of the project. While it was not completed upon the planned time set out in the gantt chart, the precautions taken that were laid out in the: ‘feasibility study’ > ‘Schedule - minimising risks’.
The final completion date was 06/06/23 meaning the project was complete 2 days before the due date yet 2 days after the intended completion date, 04/06/23. The reason why the project was still able to be completed on time was that during the planning for the time scheduling, a four day buffer zone was allowed, this could then be utilised during the project and be used as a means, by the project manager, to determine the likelihood of going over the official due date.
However, during the project, there was a point where the project was actually five days behind schedule, meaning if all following tasks were completed within the duration they were given, the project would not be completed by the due date. This was the biggest setback in the whole project and was the only point in time throughout where the project seemed to have the possibility of failing. In terms of time management and all other criteria that are to be covered in this evaluation and reflection, this was the biggest weakness overall.
- This shows the estimated start and finish date of this stage of the project.
- This shows the actual finish date of the last task in this stage of the project(right, 23/05/23).
Due to this setback, it meant that another precaution that was emphasised in the project feasibility study was utilised, this was ensuring that sufficient communication was being made between team members and that efficiency was a key priority, more so than previous(although the importance was always present throughout the project regardless). This was especially important in the Peer review/feedback and optimization stages of the project. It was made apparent, to those who would be given the feedback, of the previous setback, thus the importance of efficient work to be done by them. This was also made clear to the animation developer.
Due to this, the Peer review/feedback and optimization stage was completed in significantly less time than was initially planned - this now meant the trajectory of the time scheduling was before the official due date(however, was still behind the schedule set out by the project manager).
- This shows the dates and duration that this stage was estimated take up(left-side dates)
- / 2
and the actual dates that it took up(right-side dates)