mailto:https://www.stuvia.com/user/Wisdoms
1. Splices in rall tracks shall have: Smooth Joints
2. Hydraulic systems should have their proper fluid level checked: Daily
- If power fails during operations, the following shouldn't apply: Do your best
- If load is undetermined who is to find out if load weight does not exceed
to finish moving load where it was designated to go
crane rating at radius at which the load is to be lifted: Person responsible for lift
5. Where should climbing instructions be kept: ON Site
6. All climbing operations shall be performed under the supervision of: Quali-
fied person
- When cranes are erected, load limiting devices shall be tested for proper
setting and operation: Before crane is placed in service
- Hooks shall be equipped with latches unless the application makes the use
of the latch: Impractical
NCCCO Tower Crane / Questions and Verified Answers| Graded A| 100% Correct 1 / 3
mailto:https://www.stuvia.com/user/Wisdoms
9. Size and position of signs or panels must satisfy the limitations of: Manu-
facturer
- Fall prevention measures are needed for working at locations where you
are exposed: To a fall of 6ft or more
11. Travel distance on hand levers shall not be greater: than 14 inches from
neutral position
- For power lines rated 175KV the minimum clearance between the lines and
any part of the crane or load is: 15ft
13. All controls shall be tested by the operator at the: start of new shift
- Before each climbing operation all load members of the support system
shall be: Inspected
15. Chain slings are required to be: ID tagged
- Welding on loads suspended by the crane can only be done if the load
has: Insulated slings
17. How much does an average cubic yard of concrete weight: 4,000 lbs
18. Main power switch for tower crane is: At base of crane
19. Items not listed in the frequent inspection checklist are: Hydraulic pumps
and valves for excessive wear or damage
- When is it necessary to determine that there is no practical alternative way
to perform the needed work or to gain access to the area: Personnel Lift
- Each series of voice signals shall contain three elements stated in the
following order: Function and Direction - Distance and speed - Function stop
- When lifting personnel communication shall be maintained between three
of the next four: Person(s) being lifted - Operator - Signal person
- The condition when the tower load block or hook assembly comes in 2 / 3
mailto:https://www.stuvia.com/user/Wisdoms
contact with the upper: Two-blocking
- / 3