APM PFQ (ACTUAL / ) EXAM TEST BANK QUESTIONS
AND VERIFIED CORRECT ANSWERS GRADED A+ | LATEST
Which of the following provides the project manager with a formal overview of project quality?A Design reviews B Project definition reports.C Quality audits.D Historical experience. - ---Answers----C
When should test plans for quality control be agreed?A During quality planning.B When the live product is available for test.C At the end of the project.D Prior to handover of the output - ---Answers----A
Inspection, measurement and testing to verify that the project
outputs meet acceptance criteria. is an example of quality:
A reporting.B control.C assurance.D planning. - ---Answers----B
A review most closely linked to the phases Of the project life
cycle could be described as a: 1 / 4
A gate review.B learning review.C handover review.D audit review. - ---Answers----A
One benefit of a gate review process is:
A it allows learning from one phase of the project to be passed on to the next phase.B it stops projects that no longer meet the organisation's needs.C it allows procurement to be planned into the project life cycle.D it allows the project team to plan delivery of the next phase
- ---Answers----B
Which one of the following would best describe a post project review?A It is a personal appraisal for each team member on completion Of the project.B It appraises the products of the project.C It considers all aspects of the management of the project.D It involves only the project implementation team. - --- Answers----C
The post project review report should be:
A included in the project plan for the next similar project. 2 / 4
B restricted in circulation in case it contains critical information.C archived for use in a future audit of project management processes.D available to all project managers within the organisation - -- -Answers----D
Which of the following would be considered as a valid objective for the post project review?A Plan the next project for the project team.B Make proposals for the operation of the project deliverables.C Improve future estimating accuracy.D Plan how to complete the objectives of the project. - --- Answers----C
Which of the following would not be considered as part of the post project review?A Evaluation of the benefits of the project.B Identification of the problems that arose and their likely causes.C Review of the project's performance against the success criteria.D Review of how the team worked together to solve problems and issues. - ---Answers----A
What is the main objective of an audit? 3 / 4
A Provide assurance to the project sponsor that the project is going to finish on time and within budget.B Provide feedback to the project manager with regard to their performance in managing the project.C Provide assurance to the sponsor that the project is being managed using the agreed governance and process.D Provide a report of the current status of the project regarding cost and schedule performance. - ---Answers----C
When is it best to carry out a benefit review?A At 6—12 months after handover.B At various stages prior to handover.C At the concept phase when developing the business case D At various stages through deployment - ---Answers----A
What aspect is important to clarify when conducting scope definition?A The number of products contained in the PBS, B The boundaries and interfaces with adjacent projects.C Who is going to perform the work.D When the work is going to be performed. - ---Answers----B
How are outputs best described?A The changed circumstances or behavior that results from their use.