• wonderlic tests
  • EXAM REVIEW
  • NCCCO Examination
  • Summary
  • Class notes
  • QUESTIONS & ANSWERS
  • NCLEX EXAM
  • Exam (elaborations)
  • Study guide
  • Latest nclex materials
  • HESI EXAMS
  • EXAMS AND CERTIFICATIONS
  • HESI ENTRANCE EXAM
  • ATI EXAM
  • NR AND NUR Exams
  • Gizmos
  • PORTAGE LEARNING
  • Ihuman Case Study
  • LETRS
  • NURS EXAM
  • NSG Exam
  • Testbanks
  • Vsim
  • Latest WGU
  • AQA PAPERS AND MARK SCHEME
  • DMV
  • WGU EXAM
  • exam bundles
  • Study Material
  • Study Notes
  • Test Prep

BICSI RTPM Exam Guide Latest

QUESTIONS & ANSWERS Dec 16, 2025 ★★★★★ (5.0/5)
Loading...

Loading document viewer...

Page 0 of 0

Document Text

BICSI RTPM Exam Guide (Latest Update 2025 / 2026 Update) Actual Test Questions and Verified Answers | Grade A | 100% Correct

Question:

Post-site survey phase

Answer:

All findings are documented and placed in the project file Determine if any structural components will obstruct the cabling pathway.

Question:

Design Project Management (Phase 3)

Answer:

Change control system

  • / 4

Question:

Design Project Management (Phase 3) Change control system

Answer:

If a change is required post-site visit, a formal change request must be made in accordance with the project's change control process. One should be implemented if the project has not already identified a change control system.

Question:

Design Project Management (Phase 3) Change control system (Tasks)

Answer:

Update the project plan with any change orders or added services.

Question:

Change Control Process

Answer:

All changes should be submitted in writing to the telecommunications PM as a formal Change request All change control correspondence should be distributed by the telecommunications PM to the design team and stakeholders involved.

  • / 4

Question:

Design Project Management (Phase 4) CA (Construction Administration)

Answer:

CA is the QC process used during construction/ installation/implementation to ensure compliance with design documents.

Question:

Design Project Management (Phase 4) CA (Construction Administration Tasks)

Answer:

Periodic site inspections by PM or QC inspector. Discrepancies/ deficiencies are noted and submitted in writing to Telecommunication PM via a formal report The PM will submit the report to the site foreman to ensure items are addressed.near the end of the project the telecommunications PM and possibly the project RCDD will conduct an ICT punch list in writing and write a formal Punch List Report and submit to the site foreman for corrections.

Question:

Design Project Management (Phase 5)

Answer:

Project Closeout 3 / 4

Question:

Design Project Management (Phase 5) Project Closeout Tasks

Answer:

Recieve redline drawings and provide them to the designers for official record drawing creation Provide official record drawings for inclusion in the projects closeout documentation package.Schedule a lessons learned debriefing with stakeholders who had participation in this stage of the project.

Question:

What are the 5 phases of a Design project manager

Answer:

1) Obtain and examine contract/ project documents 2) Perform site survey 3) Change control system 4) Construction Administration 5) Project closeout

  • / 4

User Reviews

★★★★★ (5.0/5 based on 1 reviews)
Login to Review
S
Student
May 21, 2025
★★★★★

With its detailed explanations, this document helped me ace my presentation. Definitely a outstanding choice!

Download Document

Buy This Document

$1.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: QUESTIONS & ANSWERS
Added: Dec 16, 2025
Description:

BICSI RTPM Exam Guide (Latest Update Update) Actual Test Questions and Verified Answers | Grade A | 100% Correct Question: Post-site survey phase Answer: All findings are documented and placed in t...

Unlock Now
$ 1.00