BICSI RTPM Exam Guide (Latest Update 2025 / 2026 Update) Actual Test Questions and Verified Answers | Grade A | 100% Correct
Question:
Post-site survey phase
Answer:
All findings are documented and placed in the project file Determine if any structural components will obstruct the cabling pathway.
Question:
Design Project Management (Phase 3)
Answer:
Change control system
- / 4
Question:
Design Project Management (Phase 3) Change control system
Answer:
If a change is required post-site visit, a formal change request must be made in accordance with the project's change control process. One should be implemented if the project has not already identified a change control system.
Question:
Design Project Management (Phase 3) Change control system (Tasks)
Answer:
Update the project plan with any change orders or added services.
Question:
Change Control Process
Answer:
All changes should be submitted in writing to the telecommunications PM as a formal Change request All change control correspondence should be distributed by the telecommunications PM to the design team and stakeholders involved.
- / 4
Question:
Design Project Management (Phase 4) CA (Construction Administration)
Answer:
CA is the QC process used during construction/ installation/implementation to ensure compliance with design documents.
Question:
Design Project Management (Phase 4) CA (Construction Administration Tasks)
Answer:
Periodic site inspections by PM or QC inspector. Discrepancies/ deficiencies are noted and submitted in writing to Telecommunication PM via a formal report The PM will submit the report to the site foreman to ensure items are addressed.near the end of the project the telecommunications PM and possibly the project RCDD will conduct an ICT punch list in writing and write a formal Punch List Report and submit to the site foreman for corrections.
Question:
Design Project Management (Phase 5)
Answer:
Project Closeout 3 / 4
Question:
Design Project Management (Phase 5) Project Closeout Tasks
Answer:
Recieve redline drawings and provide them to the designers for official record drawing creation Provide official record drawings for inclusion in the projects closeout documentation package.Schedule a lessons learned debriefing with stakeholders who had participation in this stage of the project.
Question:
What are the 5 phases of a Design project manager
Answer:
1) Obtain and examine contract/ project documents 2) Perform site survey 3) Change control system 4) Construction Administration 5) Project closeout
- / 4