Q1. What is the primary purpose of a building code?
- Increase construction profits
- Reduce project timelines
- Protect public health, safety, and welfare
- Support property value
Rationale: Building codes exist to ensure safety, health, and structural
integrity for occupants and the public.Q2. Which document typically authorizes the start of construction work?
- Certificate of Occupancy
- Building Permit
- Inspector Report
- Design Contract 1 / 4
Rationale: Construction cannot legally begin until a building permit is
issued.Q3. Who is responsible for ensuring materials conform to approved plans?
- Property owner
- Architect
- Contractor
- Inspector
Rationale: Contractors must build according to the approved plans and
ensure materials meet specifications.Q4. Which type of inspection occurs before concrete is poured?
- Final inspection
- Insulation inspection
- Footing inspection
- Drywall inspection
Rationale: Footing inspections verify depth, width, and reinforcement
before concrete placement.Q5. What does an inspector evaluate during a framing inspection?
- Paint quality
- Structural members alignment and fastening
- Landscaping placement
- Roofing color
Rationale: Framing inspections confirm structural support systems comply
with code. 2 / 4
Q6. Which occupancy group includes schools?
- Group R
- Group E
- Group B
- Group S
Rationale: Group E covers educational facilities for six or more persons.
Q7. The minimum ceiling height for habitable rooms is generally:
- 6 ft
- 6 ft 8 in
- 7 ft
- 7 ft 6 in
Rationale: Most codes require at least 7 ft ceiling height for habitable
rooms.Q8. What must be installed in bedrooms for life safety?
- Hose lines
- Smoke alarms
- Carbon filters
- Security cameras
Rationale: Smoke alarms warn occupants early during a fire event.
Q9. Fire-rated walls are designed to:
- Reduce noise
- Increase visual appeal
- Resist fire spread for a specified time 3 / 4
- Support heavy loads
Rationale: Fire-rated assemblies slow fire spread, allowing safe
evacuation.
Q10. A Certificate of Occupancy is issued when:
- Permit fees are paid
- All inspections are passed and building is safe
- Construction begins
- Owner files a tax record
Rationale: The CO confirms code compliance and safe occupancy.
Q11. What is spalling in concrete?
- Rust formation
- Surface flaking or chipping
- Color fading
- Over-vibration
Rationale: Spalling results from moisture, freeze-thaw cycles, or corrosion.
Q12. Soil compaction is important because it:
- Improves aesthetics
- Reduces noise
- Prevents settlement and structural failure
- Lowers cost
Rationale: Proper compaction stabilizes foundations and prevents
structural issues.