- | P a g e
NCCCO Telescopic Boom Crane -Swing Cab exam with 100 Questions and answers
- Who should an operator respond to a "stop" signal from?
- Appointed signal person only
- Project manager only
- Superintendent only
- Anyone - ANSWER-d.
- Which area do truck cranes without a 5th outrigger generally
- The side
- The rear
- The front
- The outriggers - ANSWER-c.
- / 3
have no lifting capacity unless the manufacturer states otherwise?
- | P a g e
- What is the definition of "operating radius?"
- The distance from the base of the boom to the center of the
- The distance from the center of rotation of the crane to the
- The distance from the center of rotation of the crane to the
- What action does a signal person intend the operator to
- Boom down
- Swing
- Boom up
- Extend boom - ANSWER-c.
load b. The distance from the front of the crane to the center of gravity of the load
center of the load
center of gravity of the load - ANSWER-d.
perform if he extends his arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up?
- When hoisting personnel, within what percentage of level must
- 1% 2 / 3
a telescopic boom crane be in order for the gross ratings in the load chart to remain valid?
- | P a g e
- 2%
- 5%
- 8% - ANSWER-a.
- The load line of the crane you're operating contacts an
- Climb down carefully from the crane cab
- Jump down, feet together
- Stay in the cab until the lines are de-energized
- Get as far away from the crane as possible - ANSWER-c.
energized power line. There's no sign of any other danger, such as fire. What should you do?
- According to OSHA 1926.1413, how many randomly distributed
- 1 broken wire in 6 rope diameters
- 2 broken wires in 30 rope diameters
- 3 broken wires in one strand in one lay
- 2 broken wires in 6 rope diameters - ANSWER-d.
- / 3
broken wires in rotation-resistant rope are cause for replacement of the rope?