NCCCO Mobile Crane Operator Certification Exam (Latest Update 2025 / 2026) Questions and Answers | Grade A | 100% Correct (Verified Solutions)
Question:
OSHA permits hoisting of personnel by a crane as long as the employer can
show:
- the prevailing wind speed is less than 35 mph
- there is no less hazardous or practicable way
- all personnel have CPR training and first aid
- all aerial lifts on site are being used that day
Answer:
there is no less hazardous or practicable way
- / 4
Question:
before lifting an occupied personnel platform on a job site the crew must ensure they perform which of the following?
- must attend a pre-lifting meeting
- must fully deploy all outriggers
- must perform a trial lift
- all of the above
Answer:
all of the above
Question:
before lifting an occupied personnel platform on a jobsite, which of the following applies?
- must use 50% of cranes rated capacity
- must trial lift anticipated load weight
- must ensure rigging is dedicated to platform only
- all of the above
Answer:
all of the above
- / 4
Question:
which of the following standards or regulations governs the lifting of personnel in construction?
- ASME B30.5
B. OSHA 1926. 1431
C. OSHA 1910. 180
D. PCSA #4
Answer:
OSHA 1926.1431
Question:
According to OSHA 1926.1431, which of these listed below must be attached to the crane?
- anti-two-block
- swing-away
- two-way bridle
- dead section
Answer:
anti-two-block
- / 4
Question:
According to OSHA 1926.1431, which of these hoist options is prohibited?
- controlled lowering
- controlled hoisting
- hoist free fall
- hoist governor
Answer:
hoist free fall
Question:
lnside the personnel platform except for gates, how much of the perimeter must contain a grab rail for occupants?
- 25 percent
- 50 percent
- 75 percent
- 100 percent
Answer:
100 percent