Certified Construction Manager (CCM) Certification Exam Practice Test 100 Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- What is the primary responsibility of a construction manager during
- Developing marketing strategies
- Securing land purchases
- Defining project scope and objectives
- Preparing legal contracts
project planning?
Rationale: CM ensures clear scope and objectives to guide design,
budgeting, and scheduling.
2. A Work Breakdown Structure (WBS) is used mainly to:
- Estimate cost contingencies
- Break project scope into manageable components 1 / 4
- Assign legal responsibilities
- Measure team performance
Rationale: WBS decomposes scope into work packages to simplify planning
and control.
- Which contract type places the most cost risk on the contractor?
- Cost-plus-fixed-fee
- Lump sum
- Guaranteed maximum price
- Unit price
Rationale: Lump-sum contracts require contractor to deliver the project for
a fixed amount.
4. A critical path in scheduling represents:
- Activities with float
- The longest path determining project duration
- Optional work packages
- Lowest-cost tasks
Rationale: Delays in critical-path activities delay the entire project.
- Which document formally authorizes a project to begin?
- Contract
B. RFI
- Project charter
- Purchase order 2 / 4
Rationale: The charter provides authorization and defines high-level
objectives.
6. The primary purpose of value engineering is to:
- Increase project timeline
- Improve function while reducing cost
- Eliminate contractor markup
- Reduce design reviews
Rationale: Value engineering optimizes cost-effectiveness without
reducing quality.
- Which cost estimate is used during early project conception?
- Definitive estimate
- Detailed estimate
- Order-of-magnitude estimate
- Bid estimate
Rationale: It provides a rough cost range before detailed design.
- A punch list is created during which phase?
- Planning
- Design
- Procurement
- Closeout
Rationale: Punch lists identify incomplete or defective work near project
completion. 3 / 4
9. The primary purpose of a change order is to:
- Cancel a contract
- Modify scope, cost, or time
- Approve payments
- Document safety incidents
Rationale: Change orders adjust contract terms due to modifications.
10. A RACI matrix identifies:
- Cost codes
- Roles and responsibilities
- Material quantities
- Safety hazards
Rationale: RACI assigns who is Responsible, Accountable, Consulted, and
Informed.
- Which safety regulation applies to construction sites in the U.S.?
- AIA Standards
B. NFPA 101
C. OSHA 1926
D. PMI PMBOK
Rationale: OSHA 1926 governs construction safety requirements.
- What is retainage?
- Equipment rental
- Withheld payment until satisfactory work completion