Illinois Industrial Project Manager Certification Examination Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- A project manager is developing a project schedule and needs to
- Risk Register
- Critical Path Method (CPM)
- Budget Baseline
- Responsibility Assignment Matrix (RAM)
identify the sequence of activities. Which tool is most appropriate?
Rationale: CPM identifies the longest sequence of dependent
activities to determine the project duration.
- What is the primary purpose of a Work Breakdown Structure (WBS)?
- To track project costs 1 / 4
- To manage stakeholder expectations
- To decompose the project into manageable tasks
- To schedule resources
Rationale: WBS breaks the project into smaller, manageable
components to aid planning and control.
- Which of the following is a leading indicator of project risk?
- Final project cost
- Customer satisfaction survey
- Frequent scope changes
- Project closure report
Rationale: Frequent scope changes may indicate potential risk,
allowing proactive mitigation.
- When estimating project costs, the project manager should use which
- Parametric estimating
- Analogous estimating
- Bottom-up estimating
- Monte Carlo simulation
method for historical data comparison?
Rationale: Analogous estimating uses historical data from similar
projects to predict costs.
- What is the main function of the project baseline?
- To forecast risk
- To allocate resources 2 / 4
- To measure project performance against scope, schedule, and cost
- To define project stakeholders
Rationale: The project baseline serves as the reference for tracking
performance throughout the project lifecycle.
- Which project document formally authorizes a project?
- Risk Management Plan
- Project Management Plan
- Project Charter
- Scope Statement
Rationale: The project charter formally initiates the project and
authorizes the project manager to apply resources.
- During the project execution phase, the manager notices tasks are
- Add more resources
- Change the project scope
- Perform schedule variance analysis
- Update the risk register
behind schedule. What is the first step?
Rationale: Schedule variance analysis identifies the root cause of
delays before corrective actions.
8. In industrial projects, OSHA regulations primarily address:
- Environmental impact
- Quality standards
- Worker safety and health 3 / 4
- Budget management
Rationale: OSHA sets legal safety and health requirements to prevent
workplace injuries.
- Which of the following is considered a project constraint?
- Stakeholder approval
- Time, cost, and scope
- Team communication
- Risk tolerance
Rationale: Constraints are limitations within which the project must
operate; the triple constraint refers to time, cost, and scope.
- A project manager uses Earned Value Management (EVM) to
- The project is ahead of schedule
- The project is behind schedule
- The project is on budget
- The project is under budget
assess performance. If the Schedule Performance Index (SPI) is 0.85, what does it indicate?
Rationale: SPI < 1 indicates the project is behind schedule, as less
work has been completed than planned.
- Which leadership style is most effective in a crisis requiring
- Democratic
- Autocratic
- / 4
immediate action?