- What is the primary purpose of a project schedule in construction
- To provide a marketing tool
- To track project expenses
- To coordinate resources and timelines
- To train new employees
management?
Rationale: A project schedule ensures that resources, tasks, and
timelines are properly coordinated to complete the project efficiently. 1 / 4
- According to OSHA, which of the following is required for trenching
- Use of temporary ramps
- Protective systems such as sloping or shoring
- Use of ladders every 50 feet
- No additional protection is needed
deeper than 5 feet?
Rationale: OSHA mandates protective systems for trenches over 5
feet to prevent cave-ins.
- Which soil type has the highest load-bearing capacity?
- Sandy soil
- Clay soil
- Rock
- Silt
Rationale: Rock provides the highest load-bearing capacity, followed
by dense sand and gravel.
- What is the primary role of a general engineering contractor?
- Designing buildings
- Performing heavy construction and civil engineering projects
- Selling construction materials
- Performing interior design
Rationale: Class A general engineering contractors focus on heavy
civil works, such as roads, bridges, and infrastructure. 2 / 4
5. In construction contracts, “liquidated damages” refer to:
- Penalties for late payments
- Pre-determined compensation for project delays
- Refunds for defective materials
- Insurance claims
Rationale: Liquidated damages are agreed-upon amounts paid if a
contractor fails to meet the project schedule.
- Which type of concrete is best for high-strength structural
- Type I
- Type II
- Type III
- High-performance concrete (HPC)
applications?
Rationale: HPC is engineered for high strength, durability, and
workability in structural applications.
- In Hawaii, which agency regulates stormwater discharges for
- EPA only
- DOT only
- Hawaii Department of Health (DOH)
construction sites?
D. OSHA
Rationale: The Hawaii DOH administers the NPDES stormwater
program for construction activities. 3 / 4
8. The critical path in a CPM schedule refers to:
- The shortest path to completion
- The sequence of activities that determines the project duration
- Optional project tasks
- Activities with the lowest cost
Rationale: The critical path is the longest sequence of dependent
activities that determines the shortest project duration.
- What is the primary purpose of a change order?
- To fire subcontractors
- To submit a new bid
- To modify the contract scope, cost, or schedule
- To approve invoices
Rationale: Change orders formally adjust contract terms when
project conditions or requirements change.
- What is the most common method for compacting granular
- Rolling
- Vibratory piling
- Mechanical vibration
- Water saturation
soils?
Rationale: Mechanical vibration is effective for densifying granular
soils like sand and gravel.