CLC 222 Module 3 Exam Contract Management 2022 •When reviewing the contract, which of the following shall be reviewed for technical and contractual understanding? (Select all that apply)
oIncorrect: The Statement of Work
•If the COR is monitoring the contract and notices that most of the deliverables are late, this could be an indicator of a problem with the contractor's ability to perform the contract.
oCorrect: True
•A bilateral modification is used to.
oCorrect: All of these answers are correct
•When changes are made to a contract, the government must determine if the change is within ?scope.? In plain English that means the work falls under the basic intent of the original contract.
oCorrect: True
•The COR should work with the Contracting Officer if the COR identifies a need to change the current contract.
oCorrect: True
•During negotiations for a proposed change to the contract, the COR may be asked to:
oCorrect: All these responses are correct
•When a contractor performs work beyond that required by the contract without a formal change order and it is perceived that such work was ordered by the Government or caused by Government fault, this is defined as?
oCorrect: Constructive change
•An unauthorized commitment is caused by government personnel obligating the government without contract authority.
oCorrect: True
•The COR should be familiar with all the following areas of a contract:
oCorrect: All these statements are correct
•Accounting data is entered at the CLIN level with ACRNS as shorthand for tracking LOAs.
oCorrect: True