Utah E100 General Engineering Contractor Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- What is the primary purpose of a construction site safety plan?
- To comply with OSHA paperwork requirements
- To schedule workers efficiently
- To identify hazards and outline procedures to prevent accidents
- To reduce material costs
Rationale: A construction site safety plan is designed to identify
potential hazards and establish procedures to minimize the risk of accidents, not just for paperwork compliance.
2. In grading a road project, the “crown” of the road refers to:
- The total road width 1 / 4
- The maximum depth of the roadbed
- The raised center of the road for drainage
- The slope at the shoulder
Rationale: The crown is the center portion of the road surface that is
slightly higher than the edges to allow water runoff.
- Which type of bond guarantees that the contractor will perform the
- Bid bond
- Payment bond
- Performance bond
- Maintenance bond
work according to the contract?
Rationale: A performance bond ensures the contractor completes the
project according to contract terms.
4. When excavating near existing utilities, the first step should be:
- Begin digging immediately
- Notify the utility company and locate utilities
- Mark and locate all underground utilities before digging
- Use mechanical equipment without caution
Rationale: To prevent damage or accidents, all underground utilities
must be located and marked before excavation.
- What is the main reason for compaction of soil in earthwork?
- To reduce soil moisture
- To increase soil color uniformity 2 / 4
- To increase soil density and strength
- To make soil easier to remove
Rationale: Soil compaction increases density, reducing settlement
and increasing strength for supporting structures.
6. The allowable stress for a material is defined as:
- The maximum stress that will cause immediate failure
- The stress applied during testing
- The maximum stress that a material can safely withstand under
- The average stress in a material
working conditions
Rationale: Allowable stress is a safe working stress below the
material’s ultimate capacity, factoring in safety margins.
- Which survey instrument is commonly used for measuring horizontal
- Level
- Tape measure
- Theodolite
- GPS receiver
and vertical angles?
Rationale: Theodolites measure horizontal and vertical angles
accurately, essential for precise surveying.
- In reinforced concrete design, the main purpose of steel
reinforcement is:
- To reduce the concrete curing time 3 / 4
- To carry tensile stresses
- To prevent shrinkage
- To improve aesthetics
Rationale: Concrete is strong in compression but weak in tension, so
steel reinforcement carries tensile loads.
- What is the standard slope for a stable cut in dry, granular soil?
A. 1:1
B. 1.5:1
C. 2:1
D. 3:1
Rationale: A 1.5:1 slope (horizontal:vertical) is generally considered stable for dry granular soil cuts.
- Which of the following is a primary consideration when selecting
- Brand popularity
- Operator preference
- Project size and type
- Color of equipment
construction equipment?
Rationale: Equipment must be chosen based on project requirements
such as capacity, terrain, and type of work.
- In concrete mixing, what effect does too much water have?
- Speeds up curing
- Reduces strength and durability
- / 4