- Which of the following is required to obtain a Class B contractor
- Proof of 2 years’ experience in specialty contracting
- Proof of 4 years’ journey-level experience in building
- A degree in civil engineering
- Membership in a trade union
license in California?
construction
Answer: B
Rationale: California requires 4 years of experience at a journey-level
classification in the trade for a Class B license.
- What is the maximum amount a Class B contractor may contract for
without a surety bond?
A. $5,000
B. $10,000
C. $15,000
D. $20,000
Answer: C
Rationale: Class B contractors can contract up to $15,000 without a
surety bond according to state law.
- Which of the following is the main purpose of a construction lien?
- Ensure the owner pays taxes
- Allow contractors to hire subcontractors
- Secure payment for labor or materials provided
- Reduce insurance premiums 1 / 3
Answer: C
Rationale: A construction lien ensures contractors and suppliers are
paid for work or materials.
- What type of insurance is required for all Class B contractors in
- Life insurance
- Workers’ compensation insurance
- Auto insurance only
- Flood insurance
California?
Answer: B
Rationale: Workers’ compensation insurance is mandatory to protect
employees from on-the-job injuries.
- What is the primary function of a building permit?
- To certify design compliance
- To ensure compliance with building codes and safety regulations
- To reduce construction costs
- To hire subcontractors legally
Answer: B
Rationale: Building permits confirm that construction meets local code
and safety requirements.
- How long must a contractor retain project records according to
- 1 year
- 2 years
- 3 years
- 5 years
California law?
Answer: C
Rationale: Contractors are required to maintain records for at least 3
years after project completion.
7. A contractor’s license bond protects:
- The contractor from bankruptcy
- The public from incomplete or defective work
- Only the building inspector
- Subcontractors’ insurance
Answer: B
Rationale: The bond ensures the public can recover damages if a
contractor fails to complete or correct work. 2 / 3
- When must a contractor provide a written contract for projects over
- Within 10 days
- Before starting work
- After the project is 50% complete
- No contract is required
$500?
Answer: B
Rationale: California law requires a written contract for projects
exceeding $500 before work begins.
- Which of the following is considered an “unfair business practice” for a
- Using licensed subcontractors
- Misrepresenting project costs
- Maintaining records
- Completing work on time
contractor?
Answer: B
Rationale: Misrepresentation of costs or services is prohibited under
state contractor regulations.
- Which class of contractor license is required to perform general
- C-10 Electrical
building construction?
B. C-20 HVAC
- B General Building
- A General Engineering
Answer: C
Rationale: Class B is specifically for general building construction
involving two or more unrelated trades.
- What is the primary difference between a Class A and Class B
- Class A covers residential only
- Class A covers engineering projects, Class B covers building
- Class B covers commercial only
- Class A cannot subcontract
license?
construction
Answer: B
Rationale: Class A is for general engineering projects; Class B is for
building construction.