Florida Certified Residential Contractor Exam Questions And Correct Answers (Verified Answers) Plus Rationale2026 Q&A| Instant Download Pdf
- What is the maximum allowable spacing for anchor bolts in a
- 8 feet
- 6 feet
- 4 feet
- 10 feet
woodframe residence according to the Florida Building Code?
Rationale: FBC requires anchor bolts at max 6' spacing for light-frame
construction to resist uplift and shear.
- For a residential slab-on-grade, what is the minimum concrete
- 2500 psi
- 2000 psi
- 3000 psi
- 3500 psi
compressive strength typically required by the FBC?
Rationale: FBC generally requires 3000 psi concrete for slabs to achieve
durability and structural integrity.
- Which document establishes the legal relationship between the
- Specifications
- Contract agreement 1 / 3
contractor and the owner?
- Change order
- Project manual
Rationale: The contract agreement defines rights, duties, scope, and
payment terms between parties.
- What is the minimum required attic ventilation ratio for vented attics?
A. 1:150
- 1:150 unless reduced to 1:300 with proper vapor barrier
C. 1:600
D. 1:200
Rationale: FBC allows 1:300 with proper cross-ventilation and vapor
barrier, otherwise 1:150.
- When must a Notice of Commencement be recorded for a residential
- After final inspection
- Before substantial completion
- Before the first inspection
- Before the first payment to contractor
project?
Rationale: Florida law requires the Notice of Commencement be recorded
before first inspection.
- Which type of soil has the highest bearing capacity?
- Clay
- Silt
- Sand and gravel
- Peat
Rationale: Granular soils like sand/gravel provide higher load-bearing
capacity and drainage.
- What is the minimum roof slope for asphalt shingles per FBC?
A. 1:12
B. 2:12
C. 3:12
D. 4:12 2 / 3
Rationale: Asphalt shingles require at least 2:12 slope for proper drainage and performance.
- What is the standard retention period for residential construction
- 1 year
- 3 years
- 5 years
- 4 years
records in Florida?
Rationale: Florida contractors must keep project records for a minimum of
four years.
- A change order must include which of the following?
- Only cost changes
- Only schedule changes
- Scope, cost, and time adjustments
- Only owner approvals
Rationale: A valid change order adjusts the scope, cost, and timeline as
needed.
10. The purpose of a footing is to:
- Support only the slab
- Hold the walls upright
- Transfer building loads to soil
- Keep rebar aligned
Rationale: Footings distribute structural loads to soil safely.
- What tool is used to determine elevation differences on a site?
- Transit level
- Laserscanner
- Builder’s level
- Theodolite
- / 3
Rationale: Builder’s levels accurately measure elevation differences in