- What Massachusetts law regulates Home Improvement Contractors?
a) M.G.L. Chapter 93A
b) M.G.L. Chapter 142A
c) M.G.L. Chapter 152
d) M.G.L. Chapter 40A
Rationale: Chapter 142A specifically governs HIC registration,
contracts, and consumer protections.
- The Home Improvement Contractor registration program in
Massachusetts is administered by:
a) The Department of Revenue 1 / 3
b) The Office of Consumer Affairs and Business Regulation (OCABR)
c) The Board of Building Regulations
d) Secretary of State
Rationale: OCABR oversees contractor registration and enforcement
under Chapter 142A.
3. A contractor must register as an HIC if the work involves:
a) New commercial construction only
b) Electrical system installation only
c) Residential remodeling of existing structures (1–4 units)
d) Industrial buildings
Rationale: Registration applies to existing owner-occupied
residential properties with up to 4 units.
- What is required in every home improvement contract over $1,000?
a) Verbal agreement only
b) Contractor’s signature only
c) Written contract with all mandated disclosures
d) Emotional assurance
Rationale: Chapter 142A mandates written contracts including
required clauses.
5. A contractor’s registration is valid for:
- 6 months
- 1 year
- 2 years 2 / 3
- 5 years
Rationale: HIC registration renews every two years in Massachusetts.
- If a homeowner signs a home improvement contract, they have the
right to cancel within:
- 1 business day
- 3 business days
- 7 calendar days
- 10 calendar days
Rationale: Mandatory three-day cooling-off period per consumer
protection law.
- Which of the following must be included on all HIC contracts?
a) Contractor’s date of birth
b) Contractor’s tax returns
c) Contractor’s registration number
d) Homeowner’s SSN
Rationale: Registration number ensures proof of compliance with HIC
laws.
8. A construction supervisor license (CSL) is required when work involves:
a) Painting only
b) Waterproofing only
c) Structural changes to the building
d) Appliance installation only
- / 3