Tennessee BC-B (Small Commercial Contractor) Licensing Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which of the following best describes the primary role of a BC-B
- Residential remodeling only
- Large-scale commercial construction
- Small commercial construction projects
- Electrical and plumbing subcontracting
contractor?
Rationale: BC-B contractors are licensed to perform small commercial
construction projects, typically under $5 million in value.
2. Before starting a construction project, a contractor must obtain:
- A verbal agreement with the client 1 / 4
- All required permits from local authorities
- Only insurance certificates
- A subcontractor agreement
Rationale: Permits ensure that construction complies with building codes
and legal requirements.
- What is the maximum bonding requirement for a BC-B contractor in
Tennessee?
A. $50,000
B. $100,000
C. $500,000
D. $1,000,000
Rationale: Tennessee law requires BC-B contractors to maintain a surety
bond of at least $100,000 to protect clients against incomplete or defective work.
- Which document legally defines the scope of work for a construction
- Invoice
- Contract
- Permit
- Proposal
project?
Rationale: A contract clearly defines project scope, responsibilities,
payment terms, and legal obligations. 2 / 4
5. The term “change order” refers to:
- Terminating a contract
- Modifying the original scope, cost, or schedule of work
- A request for payment
- Issuing a permit
Rationale: Change orders formalize any changes to the initial project
agreement to avoid disputes.
- In Tennessee, how long must contractor records be retained?
- 1 year
- 2 years
- 5 years
- 10 years
Rationale: Contractors must keep project records, contracts, and financial
documents for five years for compliance and auditing purposes.
- Which of the following is required for all BC-B contractors in
- OSHA 500 certification
- Workers’ compensation insurance
- LEED accreditation
- EPA licensing
Tennessee?
Rationale: Workers’ compensation coverage protects employees in case of
workplace injuries and is legally required. 3 / 4
- What is the primary purpose of a construction lien?
- To report accidents
- To secure payment for labor or materials supplied
- To obtain building permits
- To hire subcontractors
Rationale: A lien ensures that contractors, subcontractors, and suppliers
can legally claim payment if unpaid.
- Which of the following materials requires special handling due to
- Concrete
- Wood
- Asbestos
- Glass
health risks?
Rationale: Asbestos is a hazardous material and must be handled
according to safety regulations to prevent health risks.
- What is the primary purpose of OSHA regulations on
- Reduce project costs
- Ensure worker safety and prevent accidents
- Improve design quality
- Expedite permit approval
- / 4
construction sites?