Georgia General Contractor License Exam (Commercial) Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which of the following is the primary purpose of a building permit?
- To increase property value
- To approve architectural design
- To ensure compliance with building codes
- To guarantee contractor payment
Rationale: Building permits are issued to verify that construction
meets local building codes and safety regulations.
- When should a contractor obtain a certificate of occupancy?
- Before construction begins
- Before the building is used or occupied 1 / 4
- After demolition of the site
- At the midpoint of construction
Rationale: A certificate of occupancy is required to confirm that a
building is safe and suitable for use.
- What is the maximum allowed slope for a residential roof without
requiring special flashing?
A. 1:12
B. 2:12
C. 3:12
D. 4:12
Rationale: Roofs with slopes less than 4:12 require special water- proofing measures to prevent leaks.
- Which soil type typically provides the best bearing capacity for
- Sandy soil
- Rock or dense gravel
- Clay
- Silt
foundations?
Rationale: Rock and dense gravel provide high load-bearing capacity
and low settlement risk.
- What is the minimum distance a fire extinguisher must be from a
- 10 feet 2 / 4
potential hazard in a commercial building?
- 75 feet
- 100 feet
- 150 feet
Rationale: Building codes generally require fire extinguishers to be
within 75 feet of hazards for accessibility.
- Which type of insurance protects a contractor from claims of property
- Workers’ Compensation
- General Liability
- Builder’s Risk
- Professional Liability
damage or injury during construction?
Rationale: General liability insurance covers bodily injury or property
damage caused by contractor operations.
- What is the minimum thickness of a concrete slab for a commercial
- 2 inches
- 3 inches
- 4 inches
- 6 inches
floor supporting light traffic?
Rationale: Standard commercial concrete slabs for light traffic are at
least 4 inches thick to handle loads safely.
- Which of the following is a standard requirement for ADA-compliant
ramps? 3 / 4
A. Slope of 1:6
B. Slope of 1:12
- Minimum width of 24 inches
- No handrails required
- How often should scaffolding be inspected on a construction site?
- Weekly
- Monthly
- Before each use
- Only after an accident
Rationale: ADA requires ramps to have a maximum slope of 1:12 and handrails for accessibility.
Rationale: OSHA requires scaffolds to be inspected before each use to
ensure safety.
- Which of the following types of concrete curing increases
- Air curing
- Water curing
- Heat curing
- Chemical curing only
strength and durability?
Rationale: Proper water curing helps cement hydration, increasing
concrete strength and durability.
- What is the main function of a vapor barrier in construction?
- To support the foundation