Road Construction Inspector Certification Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
Q1. What is the primary responsibility of a road construction inspector?
- Design roadway plans
- Approve contractor payments
- Operate construction equipment
- Ensure construction work complies with plans, specifications, and
standards
Rationale: Inspectors verify compliance; they do not design or operate
equipment.
Q2. Which soil type generally has the highest compaction difficulty?
- Gravel
- Sand 1 / 4
- Silt
- Clay
Rationale: Clay holds moisture and compacts poorly without proper
conditioning.
Q3. The Proctor test is used to determine which property of soil?
- Plasticity index
- Shear strength
- Optimum moisture content and maximum dry density
- Liquid limit
Rationale: The Proctor test identifies OMC and MDD for compaction
control.
Q4. What is the typical moisture content range allowed for compaction relative to optimum?
A. ±10%
B. ±8%
C. ±5%
D. ±2%
Rationale: Most specifications require moisture within approximately 2%
of OMC.
- / 4
Q5. A proof roll is used primarily to identify:
- Asphalt density
- Soft or unstable areas in subgrade
- Aggregate gradation
- Concrete slump
Rationale: Proof rolling reveals weak or pumping subgrade locations.
Q6. What instrument is commonly used to measure elevation differences on a roadway?
- Tape measure
- Smart level
- Automatic level (Dumpy level)
- Laser thermometer
Rationale: Automatic levels provide accurate elevation readings for grade
checks.
Q7. The purpose of a tack coat in asphalt paving is to:
- Increase asphalt stiffness
- Prevent moisture intrusion
- Promote bonding between pavement layers
- Increase skid resistance
Rationale: Tack coat ensures proper adhesion between asphalt layers. 3 / 4
Q8. What is the primary role of aggregate base in road construction?
- Provide skid resistance
- Distribute loads to subgrade
- Seal cracks
- Control drainage only
Rationale: Base layers transfer traffic loads to the subgrade.
Q9. What is the minimum slump typically required for standard roadway concrete?
- 0–1 inch
- 6–8 inches
- 2–4 inches
- 8–10 inches
Rationale: Roadway concrete generally uses a medium slump for
workability and strength.
Q10. Which test is used to determine asphalt binder grade?
- L.A. abrasion test
- Proctor test
- Performance grade (PG) testing
- Slump test
- / 4