Florida Certified General Contractor Exam Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which of the following best describes the primary purpose of a
- To guarantee the contractor’s profit
- To guarantee the project’s timely completion
- To guarantee the contractor will complete the project according to the
- To guarantee subcontractors will be paid
performance bond?
contract
Rationale: A performance bond ensures the contractor fulfills the
contractual obligations and completes the project as specified. 1 / 4
- What is the maximum amount a contractor may retain from a
- 5%
subcontractor’s payment in Florida without a written agreement?
B. 10%
C. 15%
- 0%
Rationale: Florida law prohibits a contractor from withholding payment
from a subcontractor unless there is a written agreement stating otherwise.
- Which document officially establishes the legal responsibilities and
- Invoice
- Contract
- Purchase order
- Change order
scope of work for a construction project?
Rationale: The contract defines the scope, responsibilities, and legal
obligations of all parties.
- Under Florida law, which type of insurance is required for all licensed
- Life insurance
- Workers’ compensation insurance
- Health insurance
- Professional liability insurance 2 / 4
contractors?
Rationale: Contractors with employees must maintain workers’
compensation insurance as required by Florida Statutes.
- When must a notice to owner (NTO) be served to preserve lien rights in
- Before the first delivery of materials
- Within 45 days of first furnishing labor or materials
- Within 90 days after project completion
- Within 30 days after contract signing
Florida?
Rationale: Florida law requires serving an NTO within 45 days of starting
work or providing materials to protect lien rights.
- Which of the following is considered a general condition cost?
- Lumber
- Nails
- Project superintendent’s salary
- Concrete
Rationale: General condition costs include salaries of on-site management
and indirect project expenses.
7. The term “retainage” refers to:
- Contractor’s profit
- Tax withheld from the project
- A portion of payment withheld until project completion
- Subcontractor fees 3 / 4
Rationale: Retainage is money withheld to ensure the contractor
completes the work satisfactorily.
- What is the minimum clear width for an accessible door according to
- 28 inches
- 30 inches
- 32 inches
- 36 inches
Florida Accessibility Code?
Rationale: The Florida Accessibility Code requires doors to provide a
minimum clear opening of 32 inches for accessibility.
- Which of the following is the best way to prevent soil erosion on a
- Using sandbags only
- Removing all vegetation
- Installing silt fences and sediment control measures
- Paving all soil areas
construction site?
Rationale: Silt fences and other sediment control measures prevent erosion
and sediment from leaving the site.
- The most important factor in determining the type of foundation for a
building is:
- Architectural style
- Soil bearing capacity
- / 4