NCCCO Core Mobile Crane sample Exam Question and Answers | Rated A+ Latest / What should you do on pick and carry operations?
- Correct Answer - Keep the boom as short as possible
- Correct Answer - Over the corner
- Correct Answer - Directly above the load's center of gravity
- Correct Answer - 45 ft.
What boom position would cause the greatest ground pressure when lifting with crawler cranes?
Where should the hook be positioned when preparing to hoist a light load?
According to OSHA 1926.1408, what minimum clearance must be maintained between any part of the crane/load and 850kV energized overhead power lines.
How many parts of line are required to hoist a 36,500 lb. load if the maximum allowable line pull is 9,000 lbs.? 1 / 3
- Correct Answer - 5
- Correct Answer - The effective weight of the jib
- Correct Answer - The next longest or the next shortest boom length,
- Correct Answer - During assembly/disassembly operations
- Correct Answer - It increases
- Correct Answer - OSHA Subpart CC 2 / 3
What determines the amount of deduction required for an erected jib that is not being used?
What capacity should you use when the boom length of the crane falls between the lengths listed in the load chart?
whichever is the lower capacity When is it okay to temporarily bypass a crane's overload warning system?
What happens to the leverage of the load on a crane as the boom is being lowered?
Where are the Standard Method hand signals found?
What should an operator do if a crane's load moment indicator (LMI) malfunctions?
- Correct Answer - Cease crane operations and report the condition to
the supervisor The primary purpose for a rooster sheave or Auxiliary boom point
sheave is to:
- Correct Answer - Separate the hoist lines
- Correct Answer - 10 ft.
What is the minimum allowable distance from the crane and power lines under 50k
When an operator leaves the crane, he must first:
- Correct Answer - ANSI B30.5-3.1.2, Put the load on the ground and put
all dogs or pawls in.According to OSHA 1926.1431(k)(8)(i) personnel platform lift shouldn't
be made with wind in excess of:
- Correct Answer - 20 MPH
- / 3
1926.1431(k)(8)(i)