Florida Certified Building Contractor Exam Questions And Correct Answers (Verified Answers) Plus Rationale2026 Q&A| Instant Download Pdf
- What is the primary scope of a Florida Certified Building Contractor
- Any structure of any size
- Structures up to three stories in height
- Only residential structures
- Only commercial structures
license?
Rationale: Florida Building Contractors may construct buildings up to
three stories, residential or commercial.
- Which document governs minimum construction standards in
- OSHA Code
- Florida Building Code
Florida?
C. NFPA 101
D. ANSI 117
Rationale: The Florida Building Code is the controlling authority for
construction standards statewide.
- Which contract type ensures a fixed price regardless of actual project
- Cost-plus
- Lump sum
- Time and materials
- Unit price 1 / 3
costs?
Rationale: Lump-sum contracts set a predetermined total price for the
work.
- What is the main purpose of soil compaction?
- Reduce slope
- Increase water content
- Increase soil bearing capacity
- Improve aesthetics
Rationale: Compaction reduces voids and increases the load-carrying
capability of soil.
5. A building permit expires if work does not commence within:
- 30 days
- 90 days
- 180 days
- 365 days
Rationale: Most Florida jurisdictions follow the 180-day start requirement
unless extended.
- Which test determines concrete strength?
- Slump test
- Cylinder break at 7 days
- Cylinder break at 28 days
- Air content test
Rationale: The 28-day cylinder test is the standard measure of concrete
compressive strength.
7. A change order must include:
- Only cost change
- Only time extension
- Scope, time, and cost impacts
- Only material list
Rationale: Change orders modify scope and must address cost and
schedule impacts. 2 / 3
- Who is responsible for jobsite safety?
- Architect
- Owner
- Contractor
- Inspector
Rationale: OSHA places primary workplace safety responsibility on the
employer/contractor.
- What is the typical minimum footing depth in Florida?
- 6 inches
- 8 inches
- 12 inches
- 24 inches
Rationale: The FBC generally requires at least 12 inches below
undisturbed soil or grade.
- What is the minimum compressive strength for standard residential
- 1,000 psi
- 2,000 psi
- 3,000 psi
- 4,000 psi
slab concrete?
Rationale: Most Florida residential slabs require 3,000 psi concrete.
- What is the purpose of rebar in concrete?
- Reduce cost
- Prevent cracking
- Add tensile strength
- Improve finish
Rationale: Rebar counteracts concrete’s low tensile strength.
- Which project document contains contract terms and legal
- / 3
conditions?