Florida Certified General Contractor Exam Questions And Correct Answers (Verified Answers) Plus Rationale2026 Q&A| Instant Download Pdf
- What is the primary purpose of Florida’s Building Code?
- To establish construction schedules
- To control contractor licensing
- To protect the public’s health, safety, and welfare
- To standardize architectural designs
Rationale: Building codes exist to ensure health, safety, and general
welfare in the built environment.
- A Notice of Commencement in Florida is valid for how long?
- 30 days
- 60 days
- 1 year
- 2 years
Rationale: Florida law sets NOC validity to 1 year unless an earlier
termination is recorded.
- Who is responsible for verifying soil-bearing capacity before
- City inspector
- General contractor
- Owner
- Architect 1 / 3
foundation work?
Rationale: The contractor must ensure conditions match the construction
documents and code requirements.
- What is the minimum compressive strength for standard concrete
- 1,500 psi
- 2,500 psi
- 3,000 psi
- 4,500 psi
footings used in residential construction (typical)?
Rationale: Most Florida residential footings require 2,500 psi minimum per
code and conventional practice.
- Which document is required before final payment can be released to
- Material order sheet
- Daily log
- Punch list
- Final contractor’s affidavit
the contractor?
Rationale: Florida statute requires a contractor’s affidavit confirming all
subs/suppliers are paid.
- When must a Notice to Owner be served to protect lien rights?
- After project completion
- Within 45 days of first furnishing labor/materials
- Before the permit is issued
- Within 10 days of the NOC
Rationale: A NTO must be served within 45 days of first work to preserve
lien rights.
- A contractor encounters differing site conditions. What should they do
- Continue working
- Notify the owner/architect immediately
- Stop the contract
- Increase the project cost 2 / 3
first?
Rationale: Prompt notice is required so the owner can verify and authorize
adjustments.
- What is the maximum allowed slope for a handicapped ramp?
A. 1:8
B. 1:10
C. 1:12
D. 1:20
Rationale: ADA and Florida accessibility require a maximum slope of 1:12.
- Which project delivery method gives the contractor the most cost
- Cost-plus
- Design-build
- Lump-sum (fixed price)
- CM-at-risk
risk?
Rationale: Lump-sum contracts place cost overruns entirely on the
contractor.
- OSHA requires fall protection at what height in construction?
- 3 ft
- 4 ft
- 6 ft
- 10 ft
Rationale: OSHA construction fall protection trigger height is 6 ft.
- Which insurance covers employee injuries?
- General liability
- Workers’ compensation
- Property insurance
- Builder’s risk
- / 3
Rationale: Workers’ compensation covers on-the-job employee injuries.