Colorado General Contractor Class A Exam (Unlimited) Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which type of insurance is mandatory for all Colorado contractors to
- General Liability
- Property Insurance
- Workers’ Compensation
- Professional Liability
protect employees on the job?
Rationale: Workers’ Compensation is legally required in Colorado to
cover injuries or illnesses that occur on the job.
2. The primary purpose of a construction lien is to:
- Finance equipment purchases 1 / 4
- Secure payment for labor or materials provided
- Reduce tax liability
- Protect the contractor from lawsuits
Rationale: A construction lien ensures contractors and subcontractors
can claim payment if not properly compensated.
3. In project scheduling, the critical path method (CPM) is used to:
- Determine labor costs
- Estimate material quantities
- Identify the sequence of tasks that dictates the project duration
- Calculate project profit margins
Rationale: CPM identifies tasks that directly affect project
completion time and schedules resources efficiently.
- Which document legally binds the owner and contractor regarding the
- Purchase Order
- Contract Agreement
- Change Order
- Bid Proposal
scope of work and payment?
Rationale: A contract agreement outlines responsibilities, scope, and
payment terms.
- OSHA requires construction employers to provide fall protection for
employees at heights of:
- 4 feet 2 / 4
- 5 feet
- 6 feet
- 10 feet
Rationale: OSHA standards require fall protection for general
construction at heights of 6 feet or more.
- Which soil type is most likely to require stabilization before
- Gravel
- Clay
- Sand
- Rock
construction?
Rationale: Clay soils expand and contract with moisture, often
requiring stabilization to prevent foundation issues.
7. The term “retention” in construction contracts refers to:
- Insurance premiums
- A percentage of payment withheld until project completion
- Contractor’s profit
- Labor benefits
Rationale: Retention ensures contractors complete the project
satisfactorily before full payment.
- Which of the following is considered a direct cost on a construction
- Office rent 3 / 4
project?
- Labor for on-site work
- Accountant fees
- Marketing expenses
Rationale: Direct costs are expenses directly associated with
construction work, like labor, materials, and equipment.
9. A construction change order must be:
- Verbal and informal
- Written and signed by the owner and contractor
- Not necessary for minor changes
- Only approved after project completion
Rationale: Written approval ensures both parties agree to changes,
preventing disputes.
- Which type of bond guarantees that the contractor will pay
- Performance Bond
- Payment Bond
- Bid Bond
- Warranty Bond
subcontractors and suppliers?
Rationale: A payment bond ensures that subcontractors and
suppliers are paid even if the contractor defaults.
- When estimating excavation for a foundation, which factor most
- Concrete mix design
- / 4
affects soil volume?