Illinois Tower Crane Operator Certification Examination Practice Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- What is the primary purpose of a tower crane’s load chart?
- To measure the wind speed
- To determine the crane’s lifting capacity at various radii
- To calculate the crane’s fuel consumption
- To identify crane operators
- To determine the crane’s lifting capacity at various radii
Rationale: The load chart provides the maximum load a crane can
safely lift at different boom lengths and angles, ensuring safe operation.
- Before starting a tower crane, which inspection is mandatory?
- Electrical wiring inspection 1 / 4
- Daily pre-operation inspection
- Concrete foundation strength test
- Painting and rust inspection
- Daily pre-operation inspection
Rationale: OSHA and industry standards require operators to conduct
a daily inspection to ensure the crane is in safe working condition.
- Which signal indicates “stop” in crane hand signaling?
- One hand raised with palm facing the operator
- Waving both hands horizontally
- Moving the hand in a circle
- Pointing downward
- One hand raised with palm facing the operator
Rationale: The standard hand signal for “stop” is a raised hand with
the palm toward the operator.
- What is the minimum distance a tower crane must maintain from
- 5 feet
- 10 feet
- 20 feet
- 50 feet
- 50 feet
power lines rated at 345 kV?
Rationale: OSHA requires a minimum clearance of 50 feet from high-
voltage power lines above 350 kV to prevent electrocution hazards. 2 / 4
- When is it necessary to use a tag line?
- When lifting personnel
- When controlling a load that may spin
- When painting the crane
- When inspecting bolts
- When controlling a load that may spin
Rationale: Tag lines help control loads during lifting and prevent
uncontrolled rotation or swinging.
- What is the correct response if a crane’s hoist brake fails during
- Continue lifting slowly
- Lower the load immediately if possible
- Increase engine RPM
- Remove the load from the hook
- Lower the load immediately if possible
lifting?
Rationale: Safety procedures dictate immediately lowering the load
safely to prevent accidents when the hoist brake fails.
- What is the maximum allowable wind speed for operating most tower
- 10 mph
- 20 mph
- 30 mph
- 50 mph 3 / 4
cranes?
- 30 mph
Rationale: Most manufacturers and OSHA recommend ceasing
operations when sustained wind speeds exceed 30 mph.
- Which of the following is the operator’s responsibility?
- Inspecting the crane prior to operation
- Certifying the crane itself
- Designing the lift plan
- Approving building permits
- Inspecting the crane prior to operation
Rationale: Operators are responsible for pre-operation inspections to
identify mechanical defects or hazards.
- Which device prevents a crane from lifting beyond its rated capacity?
- Load limiter
- Hoist brake
- Anti-sway device
- Boom angle indicator
- Load limiter
Rationale: Load limiters stop the hoist from lifting a load that
exceeds the crane’s rated capacity, preventing structural failure.
- When signaling a crane to raise the load, what is the correct
- Palm forward, move hand up and down
- Fist raised
- / 4
hand signal?