How much asphalt should be in front of the screed being mixed by the augers?
Answer:
The proper head of material is at the center of the auger shaft
Question:
While the paver is moving the augers should be moving
Answer:
80 - 90 % of the time
- / 3
Question:
Screed heaters can not be used to do what
Answer:
raise the heat of the mix
Question:
When matching paved joints you must have a
Answer:
Joint matcher ( sonic or shoe paddles)
Question:
The ski pole for the join matcher has to be how long
Answer:
25ft
Question:
Longitudinal (horizontal when facing down the road) joint should always be staggered how far apart
Answer:
- to 12 inches 2 / 3
Question:
While paving an unsupported edge the edge can no deviate more than how far from the string line?
Answer:
+/- 1.5"
Question:
Tapers are required on joints when the adjacent travel lanes has a difference in elevation
Answer:
greater than 1 1/2
Question:
For the rolling straight edge the deficiencies must be fixed when
Answer:
greater than 3/16' Mark 50 feet from each side of the start and end of the deficiency