New Mexico General Building Contractor (GB-98) Practice Exam 100 Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- What is the main building code adopted for commercial construction
in New Mexico?
A. IRC
B. UBC
C. IBC
D. BOCA
IBC governs commercial buildings under NM Construction Industries Division.
- Which trade requires a GB-98 contractor to subcontract with licensed
- Painting
- Insulation 1 / 3
specialists?
- Electrical
- Drywall
- Who is responsible for verifying jobsite safety compliance?
- Building officials
- The contractor
- Property owner
- Architect
- A contractor must notify the owner of material substitution that
Electrical work must be performed by a properly licensed EE98 contractor.
Contractors must ensure OSHA compliance on-site.
affects:
- Paint color
- Cost or performance
- Delivery timing only
- Warranty paperwork only
Material changes impacting cost/functionality must be disclosed.
5. The minimum footing depth in New Mexico must extend below:
- 6 inches
- Frost line only
- Frost line and to stable soil
- Surface slab
Footings must bear on undisturbed soil below frost depth. 2 / 3
6. A change order becomes valid when:
- Verbal approval from worker
- Owner receives invoice
- Both parties sign the change order
- Contractor completes the work
Written and signed change orders are legally binding.
7. Workers must be trained in fall protection at heights above:
- 10 ft
- 6 ft
- 4 ft
- 20 ft
OSHA fall protection starts at 6 ft for construction.
8. A building permit is required for:
- Painting
- Flooring replacement
- Structural modifications
- Minor repairs
- Which document sets quality standards and installation procedures?
- Insurance policy
- Specifications
- Bid tab
- / 3
Structural changes require permitted review.