Kansas General Contractor Class A Exam (Unlimited) Practice Exam Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- What is the primary purpose of a performance bond in construction
- To guarantee the contractor will complete the project according to
- To insure the building against fire damage
- To pay the subcontractors directly
- To cover the contractor’s payroll
contracts?
the contract
A
Rationale: A performance bond ensures the contractor fulfills
contractual obligations and completes the project as agreed. 1 / 4
- Which of the following is required to be licensed as a general
- Any subcontractor
- Contractors working on projects over $5,000
- Only contractors specializing in plumbing
- Contractors working exclusively on residential projects
contractor in Kansas?
B
Rationale: Kansas law requires general contractor licensing for
projects exceeding $5,000 in total contract value.
- Which insurance is specifically designed to protect employees from
- General liability insurance
- Workers’ compensation insurance
- Professional liability insurance
- Builder’s risk insurance
job-related injuries?
B
Rationale: Workers’ compensation insurance provides coverage for
employees injured on the job.
- What is the main purpose of a lien waiver?
- To prevent subcontractors from claiming unpaid balances
- To transfer ownership of materials to the contractor
- To ensure building permits are obtained
- To notify OSHA of project hazards 2 / 4
A
Rationale: Lien waivers prevent subcontractors or suppliers from
placing liens on property after receiving payment.
- Under Kansas law, who is primarily responsible for jobsite safety?
- The architect
- The subcontractor
- The general contractor
- The local building inspector
C
Rationale: The general contractor holds primary responsibility for
ensuring a safe worksite.
- What is the typical purpose of a change order?
- To adjust the project schedule
- To revise the contract price or scope of work
- To cancel the contract
- To assign subcontractors
B
Rationale: Change orders document modifications to the contract’s
price, scope, or specifications.
7. The term “critical path” in project scheduling refers to:
- The least expensive construction route
- The sequence of tasks that determines project duration
- The subcontractors’ work priorities 3 / 4
- Optional project tasks
B
Rationale: The critical path identifies activities that directly affect the
project completion date.
- What is the minimum number of hours OSHA requires for construction
- 4 hours
- 10 hours
- 30 hours
- 40 hours
safety training for new employees?
B
Rationale: OSHA mandates a 10-hour safety orientation for new
construction employees.
- Which of the following materials is most commonly used as a
- Wood
- Concrete
- Aluminum
- Glass
structural foundation in Kansas?
B
Rationale: Concrete is standard for foundations due to its durability,
strength, and resistance to soil conditions.